No project in Arlington Village, but 2 nearby
Who decides here: the Village Board of Arlington Village votes on zoning. The Columbia County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
QTS data center campus (DeForest / Town of Vienna)
Vienna, Dane County
1,600 acres
🕒 Jan 28, 2026: QTS said now is not the right time for the project and paused it.
Stopped or cancelledabout 12 miles awayStonebridge data center proposal (Town of Pacific)
Pacific, Columbia County
🕒 Nov 2025: The town chair told the developer any talks must happen in a public meeting with the who…
Reported in the news, not confirmed yet
Local votes and rules
📌 Other · Columbia County
Columbia County adopted a rule that bars county supervisors from signing agreements to keep plans private (NDAs) about data centers.
What you can do
- Get told first.
We'll email you if anything changes in Arlington Village. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Arlington Village: Wisconsin Power & Light Co. (company) or Wppi Energy (municipal mktg authority).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Wisconsin.