1 data center project in Unincorporated McPherson County

Who decides here: the McPherson County Commissioners decides on zoning for land outside city and town limits.

In Unincorporated McPherson County

Local votes and rules

πŸ“Œ Other

The county board heard the permit request (26-CUP-04) for the Leola data center and then postponed its decision after a closed session. No new date was set.

Aug 11, 2026Source

πŸ“œ Data center rules

The county drafted changes to its data center rules (Ordinance 2026-1). The draft keeps the one-mile buffer from churches, schools and homes, and adds noise limits and buffer yards. We did not find whether it was adopted.

Feb 24, 2026Source

πŸ“œ Data center rules

The county added data center rules (Chapter 5.33, Data Processing Centers) to its zoning code. Data centers need a conditional use permit and must be one mile from any church, school or home.

July 2025Source

⏸️ Pause on new data centers

Commissioners paused data center permits until the county wrote data center rules. Those rules were adopted in 2025.

Dec 2024Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Unincorporated McPherson County.
  2. Go to county meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Unincorporated McPherson County. Nothing else.

⚑ Your electric company

Depending on where you live in Unincorporated McPherson County: Montana-dakota Utilities Co. (company) or Fem Electric Assn, Inc. (not available).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in South Dakota.

πŸ™‹ Open tasks here

  • When will the McPherson County Board of Adjustment vote on permit 26-CUP-04?
  • Who is the tenant or customer for the data center?
  • How many diesel backup generators are planned?
  • Will the promised community payments be in a signed agreement?

How to help β†’