All projects
Newest activity first. Click one to see the details.
The rules in Rhode Island
What the state says about data centers, in plain words.
📜 State laws
2026 bills H7695 / S2346: tax breaks for big data centers (did not pass) · May 7, 2026
These bills would have let data centers skip property tax, equipment tax and sales tax for up to 30 years if they invest at least $400 million (or $200 million in an enterprise zone). The Senate Commerce Committee held S2346 for further study on March 10, 2026, after a long debate. The House Finance Committee held H7695 on May 7, 2026. Neither came back before the session ended, so there are no data center tax breaks in Rhode Island law. Source
2026 bills H7331 / S2776: big data centers pay for their own power lines (did not pass) · April 7, 2026
These bills would have made data centers that use 50 megawatts or more pay the cost of the power lines and other grid work needed to serve them, so other customers do not pay. H7331 also would have made them report their water use each year to the Department of Environmental Management (DEM). Both were held for further study in committee (S2776 on March 10, H7331 on April 7, 2026) and did not pass. Source
2026 bills H7270 / S2427: a separate electric rate for data centers (did not pass) · April 7, 2026
These bills would have told the Public Utilities Commission (PUC) to create a separate class of electric service for data centers that use 20 megawatts or more. The PUC wrote to the Senate committee that it understood the concern but asked for wording changes. Both bills were held for further study (S2427 on March 10, H7270 on April 7, 2026) and did not pass. Source
💡 Who pays for the power
No special electric rate for data centers yet · Oct 8, 2026
Rhode Island Energy is the main electric company. As of October 8, 2026 there is no separate rate or contract rule for very large users like data centers; the 2026 bills that would have required one did not pass. Rhode Island Energy has said its current rate case does not include costs for possible future data centers. Source
2026 rate case: PUC cut Rhode Island Energy's request and approved about $170 million in bill credits · Aug 21, 2026
Rhode Island Energy asked in November 2025 to raise electric and gas delivery rates (dockets 25-45-GE and 25-33-GE). Its own estimate was about $9.02 more per month (5.6%) on delivery for a home using 500 kWh, and about $391 more per year for gas heat. On August 21, 2026 the PUC allowed only a one-year increase, kept the company's allowed profit rate where it was, and approved about $170 million in credits that start on bills in October 2026. Officials say the electric credits will more than cover the electric increase for the next 12 months. Source
Winter 2026-27 electric supply price and the energy emergency · July 23, 2026
Rhode Island Energy asked to charge 17.029 cents per kWh for home electric supply from October 1, 2026 (summer was 11.092 cents). For a home using 500 kWh a month that is about $30.93 more per month (21.4%) (docket 26-27-EL). On July 23, 2026 Governor McKee declared an energy affordability emergency and set aside $28 million for bill credits for every home electric account. We could not confirm the PUC's final vote on the winter price. Source
💵 Tax breaks
No special state tax break for data centers · Oct 8, 2026
Rhode Island has no tax break written just for data centers. The 2026 bills that would have created one (H7695 / S2346) were held in committee and did not pass. Supporters said 42 other states offer similar breaks; critics said the state would pay for projects that would be built anyway. A town can still negotiate its own tax deal with a company. Source
🤐 Secret deals and public records
Public records law (APRA): anyone can ask · 2026
Under Rhode Island's Access to Public Records Act, every person or company can ask to see or copy records of a town or state agency. You do not have to live in Rhode Island. The agency must answer within 10 business days; it can take 20 more business days for good cause if it explains why in writing. No answer in time counts as a denial. Copies cost at most 15 cents a page; search time is free for the first hour, then at most $15 an hour. Source
Company secrets can be kept from the public · 2026
The law lets agencies hold back trade secrets and business or money information that a company gave in confidence. But they must release the rest of the document with only that part blacked out. There is no state law that bans or limits secret deals (NDAs) between towns and data center companies. Source
If your records request is denied · 2026
First ask the head of that agency to review it (answer due in 10 business days). Then you can file a complaint with the Attorney General, who can take the agency to Superior Court for you. You can also hire your own lawyer and sue in Superior Court. Source
💧 Water
Who decides on big water use · 2026
Most data centers would buy water from a local water supplier. Water suppliers that handle more than 50 million gallons a year must keep a water supply plan with the state. A supplier needs approval from the state Water Resources Board (after advice from the Health Department) before it takes a new water source or extends its mains into another town. There is no state law that makes data centers report their water use; the 2026 bill that would have done this (H7331) did not pass. Wells, wetlands and wastewater permits go through DEM. Source
🌫️ Air and generators
Backup diesel generators need a DEM air permit · 2026
A data center's backup generators need a minor source air permit from DEM's Office of Air Resources before they are installed, if each engine is 50 horsepower or larger (or 350,000 BTU per hour or more) and started up after November 15, 2007. Small permits do not require a public comment period. Big (major source) permits do: a newspaper notice, at least 30 days for comments, and a public hearing if someone asks for one. Source
Power plants and big power lines: Energy Facility Siting Board · 2026
A power plant of 40 megawatts or more, or a power line of 69,000 volts or more, is a 'major energy facility'. The state Energy Facility Siting Board gives the single final license for it, and town boards only send it their findings and advice. DEM still issues federal air and water permits. A data center that builds its own large power plant would go through this board. Source
🙋 How to have your say
Who decides a data center near you · 2026
Rhode Island has no county governments. Each of the 39 cities and towns zones all its own land. Zoning changes are sent to the Planning Board (or Commission), which reports to the Town or City Council within 45 days. The council must hold a public hearing within 65 days and decide within 45 days after the hearing. The Zoning Board of Review decides variances, special-use permits and appeals of the zoning official's decisions. Source
How you hear about a zoning change · 2026
Before the council votes on a zoning change, it must place a notice in a local newspaper once a week for 3 weeks, post it at town hall and on the town website at least 14 days ahead, and mail notice to some nearby owners at least 2 weeks ahead. At the hearing, anyone interested may speak. Source
Appeal deadlines · 2026
To fight a new zoning ordinance or zoning change in court, a resident, landowner or group of residents of that town can file in Superior Court within 30 days after it takes effect. To appeal a Zoning Board of Review decision, an affected person must file in Superior Court within 20 days after the decision is recorded and posted at the town clerk's office. Source
Find town meeting agendas · 2026
Every town council, planning board and zoning board must post its meeting notices on the Secretary of State's Open Meetings website (opengov.sos.ri.gov). You can search by the board's name and sign up for an RSS feed. Source
Comment on electric rates · 2026
The Public Utilities Commission (PUC) holds public comment hearings on Rhode Island Energy rate requests, in person in Warwick and by Zoom. You can also mail or email written comments to the Commission Clerk, naming the docket number. Source
Ask for records · 2026
Send a written request to the town's or agency's public records officer (any person can file; see 'Public records law' above). Ask for emails, agreements and plans about a data center. The answer is due in 10 business days. Source
🧾 Help with your bills
Heating help (LIHEAP) · Oct 1, 2026
Rhode Island's Low Income Home Energy Assistance Program helps pay heating bills. Applications for the 2026-27 winter open October 1, 2026, through your local Community Action Program (call 401-921-4968 to find yours). You may qualify if your household income is at or below 60% of state median income (for example about $42,252 a year for 1 person or $81,254 for 4). Apply early: last season the deadline was April 15 and grants were smaller. Source
Rhode Island Energy discount and payment plans · 2026
People who get LIHEAP can get a 25% discount on their Rhode Island Energy electric and/or gas bill; the account must be in the applicant's name. Rhode Island Energy also has payment plans for overdue bills. Households that do not qualify for LIHEAP can call 2-1-1 to ask about the Good Neighbor Energy Fund. Source
📞 Who to contact
Public Utilities Commission (PUC) · 2026
Sets electric and gas rates for Rhode Island Energy and holds public comment hearings. 89 Jefferson Blvd., Warwick. Source
Energy Facility Siting Board · 2026
Gives the final license for power plants of 40 MW or more and power lines of 69 kV or more. Its staff sits at the Division of Public Utilities and Carriers. Source
DEM Office of Air Resources · 2026
Air permits for backup generators and power plants. Source
Water Resources Board · 2026
Approves new water sources and water main extensions by water suppliers, and oversees water supply plans. Source
Attorney General · 2026
Takes complaints when a public records request is denied, and speaks for customers in utility rate cases. Source
Secretary of State: Open Meetings portal · 2026
Lists meeting notices and agendas of every town council, planning board and zoning board. Source
General Assembly: bill status · 2026
Look up any bill and its history. Data center bills are filed in January to March; the session usually ends in June. Source