Prometheus Hyperscale data center on Falls Ranch between Casper and Glenrock
Also called: Prometheus Casper
Prometheus Hyperscale had planned a 1.25-gigawatt data center and gas power plant on about 940 acres of Falls Ranch, southeast of Casper. On Oct. 28, 2026 the company said it will not build in Natrona or Converse County. The ranch owner says a new developer will take over, but has not said who. No permit or zoning request was ever filed with the county.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Natrona County Commissioners (for land outside city and town limits).
Where things stand: Status unclear Prometheus Hyperscale dropped the plan on Oct. 28, 2026. The ranch owner says the project will go on with a new, unnamed developer, with public meetings in 2027. No permit was ever filed.
❓ 5 open questions about it: see below.
Last checked Nov 1, 2026.
🕒 Latest update (Oct 29, 2026): Falls Ranch said the project will continue with a new developer it did not name, with public meetings planned for 2027.
What we know
- 📍 WhereFalls Ranch southeast of Casper, south of I-25, west of Big Muddy Creek, Unincorporated Natrona County, Natrona County
- 🏢 CompanyNot named (Prometheus Hyperscale withdrew Oct. 28, 2026)
- 🌳 Size940 acres
- ⚡ Power it needs1,250 megawatts (about as much as 1,000,000 homes)
- 🔌 Where the power comes fromNatural gas engines and turbines on site, with gas through a Black Hills Energy line. The company would not promise all phases stay off the grid.
- 💧 Wateron-site wells for offices; no city water (company)
- ❄️ Coolingclosed loop with 75% water and 25% propylene glycol (company)
- 💵 Cost$16 billion
- 👷 Jobs promised150
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Does any part of the project sit in Converse County? 🙋 I'll find out ·
- Which permits will Natrona County require, and when is the hearing? 🙋 I'll find out ·
- Which company will use it? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
- Which company will replace Prometheus Hyperscale as the developer on Falls Ranch, and will the plan stay the same size? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the news reports and the 2020 state parcel map for an exact site: none gives a parcel, address or road corner.
What happened so far
- Oct 2025Prometheus signed a deal for a ranch site near Casper, which earlier reporting said reaches into Converse County.
- May 19, 2026Converse County commissioners undid an April vote that set up an industrial park near the county line, after the state Attorney General's office objected.
- Sept 1, 2026Prometheus outlined the project at a Natrona County Commission information session.
- Oct 28, 2026Prometheus Hyperscale said it will not pursue a data center in Natrona or Converse County. It said it is still working on its Uinta County project and looking at other Wyoming sites.
- Oct 29, 2026Falls Ranch said the project will continue with a new developer it did not name, with public meetings planned for 2027.
Local votes and rules
📌 Other
On April 21, 2026, county commissioners passed a resolution to set up industrial parks that could skip the state siting review. On May 19 they took it back after the state Attorney General's office said a county without zoning can't do this. The county has no land zoning.
Drag the slider to compare the land before and now.
Where this comes from
- Casper Lands Massive 1.5-Gigawatt Data Center Project on Nearby Ranch · Cowboy State Daily · Oct 9, 2025
- After Attorney General Says Don't, Converse County Won't Fast-Track Data Centers · Cowboy State Daily · May 21, 2026
- Natrona County Residents Pack Meeting To Hear Plans For Huge 1.25-GW Data Center · Cowboy State Daily · Sept 2, 2026
- Prometheus Pushes Ahead On $32B Wyoming Data Centers As Legal Challenge Fades · Cowboy State Daily · Aug 25, 2026
- Prometheus cancels data center proposal near Casper · WyoFile · Oct 28, 2026
- Prometheus Hyperscale drops plans for $500M data center campus in Natrona County · Oil City News · Oct 28, 2026
- Falls Ranch data center project moving forward without Prometheus · County 17 · Oct 29, 2026