Related Digital data center campus in Cheyenne Business Parkway (for CoreWeave)
Related Digital is building a $1.2 billion data center campus in east Cheyenne for the AI cloud company CoreWeave. The first building should be done in late 2026. The campus could grow to 302 megawatts.
Where things stand: Ground broken October 2025. First building expected to be done in late 2026.
π Latest update (June 11, 2026): Company toured the site. About 400 workers were building the first 184,000-square-foot building.
What we know
- π WhereCheyenne Business Parkway, east Cheyenne, Cheyenne, Laramie County
- π’ CompanyRelated Digital
- ποΈ Owned byRelated Companies
- π€ Built forCoreWeave
- π³ Size115 acres
- β‘ Power it needs302 megawatts (about as much as 241,600 homes)
- π Where the power comes fromBlack Hills Energy, through underground lines from a substation, under Wyoming's large-power rate. Backup generators on site.
- π§ Waterlittle ongoing water use, about like an office building (company)
- βοΈ Coolingclosed-loop direct-to-chip liquid cooling with air-cooled chillers
- π΅ Cost$1.2 billion
- π· Jobs promised40
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Sources give 302 MW or 420 MW for the full campus. Which is right? π I'll find out
- What kind of backup generators are on site, and how many? π I'll find out
What happened so far
- Oct 7, 2025Related Digital broke ground on a $1.2 billion, up to 302 MW campus. CoreWeave leased 88 MW.
- June 11, 2026Company toured the site. About 400 workers were building the first 184,000-square-foot building.
Local votes and rules
β Approved
The City Council voted 8-2 to annex Cox Ranch (about 1,260 acres west of Roundtop Road) and zone it business park for a Skybox and ViaWest data center. In April a council committee voted 2-1 against it, and the council put it off until September. One councilor switched to yes after the developers promised to protect water flow to Crow Creek.
πΊοΈ Zoning change
Trammell Crow asked to rezone 162 acres in south Cheyenne from farm to light industrial for the Orchard Hills data center. The Planning Commission voted no unanimously on Sept. 8. The City Council has the final say, set for Oct. 12, 2026.
βοΈ Court case
A resident filed two cases in district court. One asks the court to cancel the July 13 Microsoft annexation. The other says the council's Aug. 10 vote to go to court broke the open meetings law. Both were served on the city in late September.
β Approved
The City Council gave final approval to annex about 3,460 acres for Microsoft's planned data center campus. That makes the city about 20% bigger. On June 22 the council voted 8-3 against asking for a $50 million community benefits deal. The City Planning Commission had advised against most of the plan.
π³οΈ Public vote
Residents turned in a petition with more than 3,000 signatures to put the Microsoft annexation to a public vote. About 2,700 are needed. On Aug. 10 the council voted 8-1 to ask a court whether an annexation can go to a referendum at all. The clerk was still checking signatures in late September.
β Turned down
The City Council voted down a one-year pause on new data centers. During the pause, city staff would have studied power use, electric rates, water and land values. About 50 residents spoke for about five hours. A council committee had sent it on without a recommendation on May 18. Reports differ on the count (8-1 or 9-1).
An aerial photo of the area.
Where this comes from
- Related Digital breaks ground on 302 MW data center campus in Cheyenne, Wyoming Β· Related Companies Β· Oct 7, 2025
- Inside The $1.2 Billion Data Center Campus Being Built In Cheyenne Β· Cowboy State Daily Β· June 14, 2026