Being built

Microsoft data center on HR Ranch Road, east Cheyenne

Microsoft is building another data center on HR Ranch Road in east Cheyenne. Its size has not been made public.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Cheyenne City.

Where things stand: Being built Under construction as of September 2026.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Sept 2026): Local reporting said construction is underway at Microsoft's HR Ranch Road data center.

What we know

  • 📍 WhereHR Ranch Road, east Cheyenne, Cheyenne, Laramie County
  • 🏢 CompanyMicrosoft
  • 👤 Built forMicrosoft

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How big is the HR Ranch Road data center, and when will it open? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the news reports and the 2020 state parcel map for an exact site: none gives a parcel, address or road corner.

    What happened so far

    • July 2025
      Microsoft said heavy earthwork would run July to November 2025, with JE Dunn as general contractor and building finished around early 2026.
    • Sept 2026
      Local reporting said construction is underway at Microsoft's HR Ranch Road data center.

    Local votes and rules

    🗺️ Zoning change

    City Council gave final approval to annex 162 acres in south Cheyenne and zone it light industrial for Trammell Crow's Orchard Hills data center. This overruled the Planning Commission's no vote. A motion to delay to January failed.

    Oct 12, 2026

    ✅ Approved

    The City Council voted 8-2 to annex Cox Ranch (about 1,260 acres west of Roundtop Road) and zone it business park for a Skybox and ViaWest data center. In April a council committee voted 2-1 against it, and the council put it off until September. One councilor switched to yes after the developers promised to protect water flow to Crow Creek.

    Sept 28, 2026

    🗺️ Zoning change

    Trammell Crow asked to rezone 162 acres in south Cheyenne from farm to light industrial for the Orchard Hills data center. The Planning Commission voted no unanimously on Sept. 8. The City Council has the final say, set for Oct. 12, 2026.

    Sept 8, 2026

    ⚖️ Court case

    A resident filed two cases in district court. One asks the court to cancel the July 13 Microsoft annexation. The other says the council's Aug. 10 vote to go to court broke the open meetings law. Both were served on the city in late September.

    Sept 3, 2026

    ✅ Approved

    The City Council gave final approval to annex about 3,460 acres for Microsoft's planned data center campus. That makes the city about 20% bigger. On June 22 the council voted 8-3 against asking for a $50 million community benefits deal. The City Planning Commission had advised against most of the plan.

    July 13, 2026

    🗳️ Public vote

    Residents turned in a petition with more than 3,000 signatures to put the Microsoft annexation to a public vote. About 2,700 are needed. On Aug. 10 the council voted 8-1 to ask a court whether an annexation can go to a referendum at all. The clerk was still checking signatures in late September.

    July 2026

    ✋ Turned down

    The City Council voted down a one-year pause on new data centers. During the pause, city staff would have studied power use, electric rates, water and land values. About 50 residents spoke for about five hours. A council committee had sent it on without a recommendation on May 18. Reports differ on the count (8-1 or 9-1).

    May 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Cheyenne Woman Asks Court To Overturn 3,500-Acre Microsoft Data Center Annexation · Cowboy State Daily · Sept 25, 2026
    2. HR Ranch Road datacenter construction · Microsoft Local · 2025

    See something wrong? Tell us and we'll fix it.