Microsoft data centers in Cheyenne (North Range, Cheyenne Business Parkway, Bison Business Park)

Microsoft has run data centers in Cheyenne since 2012. It is the biggest taxpayer in the city. More than 320 Microsoft staff work there.

βœ” ConfirmedSourceLast checked: Oct 2026

Where things stand: Running since 2012. Two more opened in 2021.

πŸ•’ Latest update (Oct 8, 2026): We also checked 2025 satellite images (Sentinel-2) of Microsoft's Bison Business Park site east of South Greeley Highway: they show finished data center halls there.

What we know

  • πŸ“ Where518 Logistics Drive in North Range Business Park, west Cheyenne, north of I-80. Microsoft also runs data centers in Cheyenne Business Parkway (east Cheyenne) and Bison Business Park (east of South Greeley Highway)., Cheyenne, Laramie County
  • 🏒 CompanyMicrosoft
  • πŸ‘€ Built forMicrosoft
  • πŸ”Œ Where the power comes fromBlack Hills Energy, under its large power contract rate. Microsoft says it pays for its own grid upgrades.
  • ❄️ Coolingdirect evaporative cooling that uses water less than 10% of the year (company)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

πŸ”Ž What we checked

  • Oct 8, 2026: We checked USGS satellite images: they show a large data center campus (long flat-roofed halls, parking and power equipment) at the pin, just north of I-80.

What happened so far

  • 2012
    Microsoft built its first Cheyenne data center.
  • Nov 22, 2021
    Microsoft opened two new data centers, in Cheyenne Business Parkway and Bison Business Park.
  • Oct 8, 2026
    We also checked 2025 satellite images (Sentinel-2) of Microsoft's Bison Business Park site east of South Greeley Highway: they show finished data center halls there.

Local votes and rules

βœ… Approved

The City Council voted 8-2 to annex Cox Ranch (about 1,260 acres west of Roundtop Road) and zone it business park for a Skybox and ViaWest data center. In April a council committee voted 2-1 against it, and the council put it off until September. One councilor switched to yes after the developers promised to protect water flow to Crow Creek.

Sept 28, 2026

πŸ—ΊοΈ Zoning change

Trammell Crow asked to rezone 162 acres in south Cheyenne from farm to light industrial for the Orchard Hills data center. The Planning Commission voted no unanimously on Sept. 8. The City Council has the final say, set for Oct. 12, 2026.

Sept 8, 2026

βš–οΈ Court case

A resident filed two cases in district court. One asks the court to cancel the July 13 Microsoft annexation. The other says the council's Aug. 10 vote to go to court broke the open meetings law. Both were served on the city in late September.

Sept 3, 2026

βœ… Approved

The City Council gave final approval to annex about 3,460 acres for Microsoft's planned data center campus. That makes the city about 20% bigger. On June 22 the council voted 8-3 against asking for a $50 million community benefits deal. The City Planning Commission had advised against most of the plan.

July 13, 2026

πŸ—³οΈ Public vote

Residents turned in a petition with more than 3,000 signatures to put the Microsoft annexation to a public vote. About 2,700 are needed. On Aug. 10 the council voted 8-1 to ask a court whether an annexation can go to a referendum at all. The clerk was still checking signatures in late September.

July 2026

βœ‹ Turned down

The City Council voted down a one-year pause on new data centers. During the pause, city staff would have studied power use, electric rates, water and land values. About 50 residents spoke for about five hours. A council committee had sent it on without a recommendation on May 18. Reports differ on the count (8-1 or 9-1).

May 26, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Microsoft announces intent to expand datacenter operations in Cheyenne Β· Microsoft Β· April 14, 2026
  2. Microsoft expands cloud services with two new datacenters in Wyoming Β· Microsoft Azure Β· Nov 22, 2021
  3. Data Center Boom Powers Cheyenne's Push For Annexation Β· Cowboy State Daily Β· April 3, 2026
  4. Laramie County parcel 13670510100400: North Range Business Park 8th Filing, Lot 1 Block 15, 518 Logistics Dr, owner Microsoft Corp (111.9 acres) Β· Wyoming county parcels (2020 tax roll), Wyoming Office of State Lands and Investments Β· Oct 8, 2026
  5. Microsoft CYS Datacenter (outline) Β· OpenStreetMap contributors Β· Oct 8, 2026
  6. Microsoft Bison Business Park Data Center (outline) Β· OpenStreetMap contributors Β· Oct 8, 2026

See something wrong? Tell us and we'll fix it.