Approved, not built yet

Project Tamarack (Starwood Digital Ventures) in West Columbia

Also called: Project Tamarack

A $12 billion data center complex planned near West Columbia in northern Mason County. It would need about 2.16 gigawatts of power from the regular grid. The company says it will use closed-loop cooling and pay for its own grid upgrades. Under the 2025 state law HB 2014, certified projects do not have to follow county or city zoning, noise and similar local rules.

โœ” ConfirmedSourceLast checked: Oct 8, 2026

Where things stand: State certified it as a high impact data center in September 2026. No construction date announced.

๐Ÿ•’ Latest update (Sept 3, 2026): Gov. Morrisey announced the $12 billion project and its state high impact data center certification at the Chamber of Commerce Business Summit.

What we know

  • ๐Ÿ“ WhereWest Columbia area, about 20 miles north of the Monarch campus (the old Clements State Tree Nursery is not part of the site), Unincorporated Mason County, Mason County
  • ๐Ÿข CompanyStarwood Digital Ventures
  • ๐Ÿ›๏ธ Owned byStarwood Capital Group
  • โšก Power it needs2,160 megawatts (about as much as 1,728,000 homes)
  • ๐Ÿ”Œ Where the power comes fromPower from the existing Appalachian Power (AEP) grid; the company says power lines are already on the property.
  • โ„๏ธ Coolingclosed-loop cooling
  • ๐Ÿ’ต Cost$12 billion
  • ๐Ÿ‘ท Jobs promised300

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 3, 2026
    Gov. Morrisey announced the $12 billion project and its state high impact data center certification at the Chamber of Commerce Business Summit.

Local votes and rules

๐Ÿ“Œ Other

After residents pushed for a response about the Monarch data center near Point Pleasant, the county commission sent state lawmakers a letter asking to change HB 2014. It asks that counties get a say on where data centers can go, and that the host county's view count heavily in the state's site score.

Aug 20, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Governor Morrisey announces more than $81 billion in new investment at West Virginia Business Summit ยท Office of the Governor of West Virginia ยท Sept 3, 2026
  2. Second certified data center announced for Mason County ยท West Virginia Public Broadcasting ยท Sept 3, 2026
  3. Starwood Digital Ventures announces data center for Mason County ยท WSAZ ยท Sept 3, 2026
  4. Project Tamarack ยท Starwood Digital Ventures (project website) ยท Sept 2026