Being builtBig (AI-size): 1,300 megawatts

Lighthouse data center campus (Port Washington)

Also called: Vantage Lighthouse, Stargate Wisconsin, OpenAI/Oracle Port Washington

Vantage Data Centers is building a $15 billion AI data center campus for OpenAI and Oracle on about 670 acres in Port Washington. It plans four buildings that need about 1.3 gigawatts of power. A $1.4 billion power line project has been proposed to serve it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Port Washington City.

Where things stand: Being built Under construction since late 2025; finish expected around 2028.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (April 7, 2026): City voters approved a referendum that requires a public vote on future TIF districts over $10 million. It does not affect this project.

What we know

  • 📍 WhereNorth side of Port Washington, on both sides of Highland Drive west of I-43 (first-phase land bought by VDC Wisco Realty Investments 1 LLC), Port Washington, Ozaukee County
  • 🏢 CompanyVantage Data Centers
  • 👤 Built forOpenAI and Oracle
  • 🌳 Size670 acres
  • ⚡ Power it needs1,300 megawatts (about as much as 1,040,000 homes)
  • 🔌 Where the power comes fromWe Energies; Vantage said it would pay for all the power upgrades through a special electric rate.
  • 🗼 New power linesYes
  • ❄️ Coolingclosed-loop liquid cooling
  • 💵 Cost$15 billion
  • 💸 Tax breaksThe city approved a $458 million tax increment financing (TIF) district to support the project.
  • 👷 Jobs promised1,000
  • 🤐 Privacy agreement (NDA)No

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the campus use per day? 🙋 I'll find out ·
  • How many diesel backup generators will be on site? 🙋 I'll find out ·
  • What is the route of the proposed new power line? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked USGS satellite images: they still show farm fields; the images are older than the late-2025 groundbreaking, so county parcel records (owned by Vantage's VDC Wisco companies) confirm the site.

    What happened so far

    • 2025
      A ceremonial groundbreaking was held in late 2025. Residents started an effort to recall the mayor.
    • Aug 2025
      The Port Washington Common Council approved the development agreement.
    • Oct 23, 2025
      Vantage, OpenAI and Oracle announced the $15 billion Lighthouse campus as part of the Stargate AI project.
    • April 7, 2026
      City voters approved a referendum that requires a public vote on future TIF districts over $10 million. It does not affect this project.

    Local votes and rules

    🗳️ Public vote

    Port Washington voters approved a resident-led rule, 2,710 to 1,371, that makes any new tax deal (TIF district) over $10 million need voter approval. Residents pushed for it after the city made a $458 million TIF district for the OpenAI-Oracle data center. That project is not affected. Business groups sued to stop the vote, but a judge let it go ahead.

    April 7, 2026

    🗳️ Election

    A resident group opposed to the Lighthouse data center filed a petition to recall Port Washington's mayor. The city clerk said it was several hundred signatures short of the 1,591 needed, so no recall election was held.

    Feb 16, 2026

    🤝 Agreement with the company

    Port Washington's Common Council approved the development deal for the $15 billion Vantage 'Lighthouse' data center campus, later tied to OpenAI and Oracle. The city also made a tax deal (TIF district) to help pay for it.

    Aug 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. ChatGPT maker, Oracle are tenants of $15 billion Port Washington data center · Urban Milwaukee / Wisconsin Public Radio · Oct 23, 2025
    2. Controversial $15 billion data center breaks ground in Port Washington · TMJ4
    3. Port Washington data center referendum · Civic Media · April 8, 2026
    4. At least four Wisconsin communities signed secrecy deals for data centers · Milwaukee Neighborhood News Service / Wisconsin Watch · Feb 1, 2026
    5. Data Centers Power Wisconsin Construction Boom Despite Public Backlash · Urban Milwaukee / Wisconsin Public Radio · Sept 30, 2026
    6. City paves way for data center, Vantage buys land · Ozaukee Press · July 2, 2025
    7. Parcels owned by VDC Wisco Realty Investments 1 LLC · Wisconsin Statewide Parcel Map (V12), State Cartographer's Office / Wisconsin DOA · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.