Built & runningBig (AI-size): 315 acres

Microsoft Fairwater AI data center campus (Mount Pleasant)

Also called: Fairwater, Fairwater 1, Microsoft Mount Pleasant data center

Microsoft's first Fairwater AI data center in Mount Pleasant cost about $3.3 billion and started running in 2026. Microsoft has called it one of the world's most powerful AI data centers. Some neighbors have sued over noise from cooling equipment and generators.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Built & running The first building opened in 2026. A second phase is being built next to it.

❓ 4 open questions about it: see below.

📣 Report noise, water or power bill changes

Last checked Oct 8, 2026.

🕒 Latest update (July 1, 2026): Three nearby Sturtevant residents filed a federal class action lawsuit against Microsoft over noise from the data center.

What we know

  • 📍 Where4800 90th Street, west of I-94 in the village of Mount Pleasant (319-acre Microsoft parcel 151032233004010), Mount Pleasant, Racine County
  • 🏢 CompanyMicrosoft
  • 🏛️ Owned byMicrosoft
  • 👤 Built forMicrosoft
  • 🌳 Size315 acres
  • 💵 Cost$3.3 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much electricity does the Fairwater data center use at full power? 🙋 I'll find out ·
  • How many diesel backup generators are on the site? 🙋 I'll find out ·
  • How much water does the site use each day? 🙋 I'll find out ·
  • What happened with the noise lawsuit filed in July 2026? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked USGS satellite images: they are older than construction and show farm fields and an existing substation; the Microsoft-owned parcel and the OpenStreetMap outline of the data center confirm the site.

    What happened so far

    • Sept 2025
      Microsoft said it would spend $4 billion more on a second, similar data center in the area, on top of the $3.3 billion first phase.
    • April 2026
      Microsoft said the Fairwater data center was going live ahead of schedule.
    • April 2026
      Neighbors north of the site reported a humming noise. Microsoft said cooling fans running at high speed during start-up caused it and made changes.
    • July 1, 2026
      Three nearby Sturtevant residents filed a federal class action lawsuit against Microsoft over noise from the data center.

    Local votes and rules

    ⚖️ Court case

    Three nearby residents filed a federal class action lawsuit against Microsoft over humming noise from its new Mount Pleasant data center. Microsoft said cooling fans at start-up caused the noise and it made changes.

    July 1, 2026

    ✅ Approved

    Mount Pleasant's Village Board unanimously approved plans for 15 more Microsoft data center buildings, with almost 9 million square feet and three new substations.

    Jan 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Microsoft's $3.3B Fairwater AI Data Center Goes Live Ahead of Schedule in Wisconsin · The Energy Mag · April 20, 2026
    2. Residents sue Microsoft over noise from new Mount Pleasant data center · Urban Milwaukee / Wisconsin Public Radio · July 3, 2026
    3. Data Centers Power Wisconsin Construction Boom Despite Public Backlash · Urban Milwaukee / Wisconsin Public Radio · Sept 30, 2026
    4. At least four Wisconsin communities signed secrecy deals for data centers · Milwaukee Neighborhood News Service / Wisconsin Watch · Feb 1, 2026
    5. Parcel 151032233004010, 4800 90th St (Microsoft Corporation, 319 acres) · Wisconsin Statewide Parcel Map (V12), State Cartographer's Office / Wisconsin DOA · Oct 8, 2026
    6. Microsoft Fairwater AI Datacenter (map outline) · OpenStreetMap · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.