Balloonist data center campus (Menomonie)

Also called: Balloonist LLC, Menomonie data center

Balloonist LLC planned a $1.6 billion data center on about 320 acres in Menomonie. After strong public pushback over secrecy and water use, the project was put on hold. The company still owns the land and would need new zoning under the city's coming data center rules.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: On hold. The company owns the land, but the city is still writing new data center zoning rules. The company would then have to ask for new zoning.

πŸ•’ Latest update (Aug 2026): The City Council discussed a draft data center ordinance: 800-foot setbacks, a water-saving plan and a bond to restore the land if the site closes. Final adoption is aimed for the end of 2026.

What we know

  • πŸ“ WhereAbout 320 acres along County Highway B, annexed into the city from the Town of Red Cedar, Menomonie, Dunn County
  • 🏒 CompanyBalloonist LLC
  • 🌳 Size320 acres
  • πŸ’§ Water75,000 gallons a day
  • πŸ’΅ Cost$1.6 billion
  • πŸ‘· Jobs promised75
  • 🀐 Secret deal (NDA)Yes. The city signed a secret deal (NDA) with Balloonist LLC in February 2024. Balloonist LLC is the same company name that signed an NDA in Beaver Dam for Meta's data center.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Feb 2024
    The city signed a secret deal (NDA) with Balloonist LLC.
  • July 2025
    Balloonist LLC asked the city to annex the land and zone it industrial. The company announced a $1.6 billion plan.
  • Aug 2025
    The City Council approved the rezoning, 8-3.
  • Sept 2025
    Balloonist LLC bought the land. Talks on a tax deal (TIF) were paused, and the mayor put the project on hold.
  • Dec 2, 2025
    Residents protested the project in Dunn County.
  • Jan 2026
    The City Council took data centers out of the 'warehousing' zoning definition.
  • Aug 2026
    The City Council discussed a draft data center ordinance: 800-foot setbacks, a water-saving plan and a bond to restore the land if the site closes. Final adoption is aimed for the end of 2026.

Local votes and rules

πŸ“œ Data center rules

Menomonie is writing data center zoning rules. The draft has an 800-foot setback, a water-saving plan, and a bond to restore the land if the site closes. A revised draft goes to the council in September and the Planning Commission in October, with a possible vote by the end of 2026.

Aug 2026

πŸ—³οΈ Election

Menomonie voters elected Matthew Crowe as mayor over the sitting mayor. Crowe opposed the data center and said the city had not been open about it.

April 7, 2026

πŸ—ΊοΈ Zoning change

Menomonie took data centers out of its 'warehousing' zoning definition, so a data center can no longer be built as if it were a warehouse.

Jan 2026

πŸ—ΊοΈ Zoning change

Menomonie's City Council voted 8-3 to annex and rezone land to industrial for Balloonist LLC's planned $1.6 billion data center. The project was later put on hold after public pushback.

Aug 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something