Being built
Keel Grant Node AI data center (former Bitcoin mine)
Also called: Grant Node Data Center, former Bitfarms Moses Lake site
Keel Infrastructure is replacing an old Bitcoin mining site in Moses Lake with a one-story data center for AI computing of about 18 MW. No customer has been announced.
Where things stand: Redevelopment under way in 2026; no tenant named.
๐ Latest update (Aug 12, 2026): Local news reported Keel is turning the old mine into a single-story AI data center.
What we know
- ๐ Where7906 Randolph Road NE, Moses Lake, Moses Lake, Grant County
- ๐ข CompanyKeel Infrastructure
- โก Power it needs18 megawatts (about as much as 14,400 homes)
- ๐ Where the power comes fromGrant County PUD
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who will use the Grant Node data center? ๐ I'll find out
- How much water will it use? ๐ I'll find out
- How many backup generators will it have? ๐ I'll find out
๐ What we checked
- Oct 8, 2026: We checked satellite photos: large industrial buildings stand at the mapped address next to Grant County International Airport.
What happened so far
- April 2026Keel shut down Bitcoin mining at the Moses Lake site.
- Aug 12, 2026Local news reported Keel is turning the old mine into a single-story AI data center.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- Keel advances Moses Lake data center as AWS speculation grows ยท Source ONE News ยท Aug 12, 2026
- Sentinel-2 cloudless satellite image of the site (2025) ยท EOX IT Services (Sentinel-2, Copernicus) ยท Oct 8, 2026
See something wrong? Tell us and we'll fix it.