Being built
Microsoft Malaga data center campus
Microsoft is building the first of up to three large data center buildings on about 100 acres in Malaga. A Microsoft spokesperson said in 2025 that the first building should be fully running by late 2026. Microsoft also bought land next door for possible growth.
Where things stand: First of up to three buildings under construction since 2023; Microsoft said it would be fully running by late 2026.
๐ Latest update (2023): Construction began on the first data center building.
What we know
- ๐ Whereoff the Malaga-Alcoa Highway in Malaga, south of Wenatchee, Chelan County
- ๐ข CompanyMicrosoft
- ๐๏ธ Owned byMicrosoft
- ๐ค Built forMicrosoft
- ๐ณ Size102.5 acres
- ๐ Where the power comes fromChelan County PUD
- ๐ง WaterColumbia River (new pump system)
- โ๏ธ CoolingColumbia River water pumped in for cooling (2023 plan: about 121,000 gallons a day per building)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the first Malaga building running now? ๐ I'll find out
- When will buildings two and three be built? ๐ I'll find out
- How many diesel backup generators does the campus have? ๐ I'll find out
- How much water does it use per day today? ๐ I'll find out
What happened so far
- April 2022Microsoft bought 102.5 acres in Malaga for about $9.2 million.
- 2023Construction began on the first data center building.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- Microsoft planning three new data centers in Central Washington ยท Bisnow ยท March 20, 2023
- Report outlines economic impact of Microsoft's Central Washington data centers ยท 425 Business ยท June 26, 2025
- Understanding Microsoft datacenters in Central Washington ยท Microsoft ยท 2026
See something wrong? Tell us and we'll fix it.