Former Vermont Yankee nuclear plant site (data center ruled out)

Also called: Vermont Yankee, PowerTransitions Vernon

PowerTransitions, a Texas company, leased the old Vermont Yankee nuclear plant site in Vernon. In June 2026 a data center was one of the ideas talked about. In September 2026 the company told residents it has no plan for a data center and wants to build a large battery site instead. Nothing has been filed with the state yet.

✔ ConfirmedSourceLast checked: Oct 8, 2026

Where things stand: A data center was floated in June 2026. In September 2026 the company said it has no plan to build one; it now wants a big battery site.

🕒 Latest update (Sept 2026): At a Vernon community meeting, PowerTransitions said it has no plan to build a data center. It now proposes a battery storage site of 110 to 440 MW.

What we know

  • 📍 Where320 Governor Hunt Road, the former Vermont Yankee nuclear plant site (about 140 acres), Vernon, Windham County
  • 🏢 CompanyPowerTransitions
  • 🌳 Size140 acres
  • 🔌 Where the power comes fromThe old nuclear plant site has big power line connections. The state said any data center there would need to make its own power.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the deal between the state and PowerTransitions rule out a data center on the site for good? 🙋 I'll find out

What happened so far

  • June 15, 2026
    Texas company PowerTransitions has leased the old Vermont Yankee site. The town planning chair said a battery site, small nuclear reactors and a data center had all been talked about.
  • June 17, 2026
    State Public Service Commissioner said any data center there would need to make its own power, and the state prefers a project that makes energy.
  • Sept 2026
    At a Vernon community meeting, PowerTransitions said it has no plan to build a data center. It now proposes a battery storage site of 110 to 440 MW.
🛰️ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Energy development company inks lease deal for Vermont Yankee property · Vermont Public (via Connecticut Public) · June 15, 2026
  2. Vernon community and the state grapple with potential redevelopment of Vermont Yankee site · VTDigger · June 17, 2026
  3. Energy development company makes its pitch for Vermont Yankee property in Vernon · Vermont Public · Sept 25, 2026
  4. Absent state action, Vermont towns move to block data centers · Seven Days · Sept 9, 2026
  5. Vermont Yankee (site address) · BHI Energy

See something wrong? Tell us and we'll fix it.