Army data center at Dugway Proving Ground (CyrusOne)

Also called: CyrusOne Dugway

The U.S. Army wants a large AI data center on about 1,200 acres at Dugway Proving Ground, built and run by CyrusOne. Nothing has been signed. The Goshute tribe has voiced opposition.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Army picked CyrusOne for exclusive talks in 2026. No lease signed yet; target opening fiscal 2029.

๐Ÿ•’ Latest update (April 2026): The Army picked Dugway and CyrusOne for exclusive talks on a hyperscale data center campus.

What we know

  • ๐Ÿ“ WhereDugway Proving Ground (U.S. Army land), Unincorporated Tooele County, Tooele County
  • ๐Ÿข CompanyCyrusOne
  • ๐Ÿ›๏ธ Owned byFunds managed by KKR and BlackRock
  • ๐Ÿ‘ค Built forU.S. Army (AI computing)
  • ๐ŸŒณ Size1,200 acres
  • โšก Power it needs1,000 megawatts (about as much as 800,000 homes)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 2026
    The Army picked Dugway and CyrusOne for exclusive talks on a hyperscale data center campus.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something