Joule data center campus near McCornick (between Delta and Fillmore)
Also called: Joule HP Compute Campus, Joule Energy and Data Center Campus
A very large data center campus on about 4,000 acres of former farmland in Millard County. It will make its own power with gas engines and solar. The company says it could grow to 12 gigawatts by 2032. No tenant has been named.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Millard County Commissioners (for land outside city and town limits).
Where things stand: Being built County rezoned the land in August 2025. Work began in November 2025; first 455 MW targeted for late 2026.
❓ 3 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (Nov 2025): Joule broke ground on the campus.
What we know
- 📍 WhereAbout 11000 N McCornick Road (Fillmore address grid), McCornick area between Fillmore and Delta, Unincorporated Millard County, Millard County
- 🏢 CompanyJoule Capital Partners
- 🌳 Size4,000 acres
- ⚡ Power it needs12,000 megawatts (about as much as 9,600,000 homes)
- 🔌 Where the power comes fromIts own gas power plant on site (Caterpillar gas engines), plus solar. Not tied to the grid.
- 🗼 New power linesNo
- 💧 WaterExisting farm groundwater rights (about 10,000 acre-feet, per the company)
- ❄️ Coolingclosed-loop water cooling (company claim)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which company will use the data centers? 🙋 I'll find out ·
- How much water will it actually pump per day? 🙋 I'll find out ·
- Has the state air quality agency issued permits for the gas engines? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: the county's hearing notice for the rezoning lists the land parcel by parcel, around 11000 N McCornick Road. We placed the pin at the middle of those parcels.
What happened so far
- Aug 5, 2025Millard County Commission voted unanimously to rezone the land from farm to heavy industrial.
- Nov 2025Joule broke ground on the campus.
Local votes and rules
🗺️ Zoning change
County commissioners rezoned about 4,000 acres of farm land (Triple C Farms, 11000 N McCornick Road) to heavy industrial for a Joule Capital Partners data center campus northwest of Fillmore. A conditional use permit was still needed to build.
Drag the slider to compare the land before and now.
Where this comes from
- Millard data center to break ground and bring promise to rural Utah · KSL · Nov 2025
- AI data centers are coming to central Utah · Sanpete Messenger · Feb 5, 2026
- 'Screaming into the void' over two data centers in central Utah · KJZZ · June 3, 2026
- Caterpillar to support multi-gigawatt data center project in Utah · Power Engineering · 2025
- What to know about data center plans in Utah · ABC4 · 2026
- Joule data center Utah · MEXC News · 2025
- Notice of public hearing, zone change Z-2025-036 (Joule Capital Partners LLC), about 4,000 acres at approx. 11000 N McCornick Road · Millard County · July 2025
- Millard County parcels (statewide parcel layer), parcels 5307-*, 5311-*, 5312-*, 5313-*, 5872-*, 5873-*, 5874-*, 5875, 5878, 5880, 5884-*, 5885, 5907-* · Utah Geospatial Resource Center (statewide parcels) · Oct 8, 2026
See something wrong? Tell us and we'll fix it.