Nebo North data center campus near Mona (Project Nebo)
Also called: Project Nebo, Nebo North LLC
A $10 billion data center campus planned on 361 acres near Mona, with up to 10 large buildings and up to 750 MW of power. The county approved a permit in April 2026; neighbors say they were left in the dark.
Where things stand: County Planning Commission granted a conditional use permit on April 15, 2026. Site plan and building permits still needed.
๐ Latest update (Sept 8, 2026): Residents spoke against the project at the Juab County Commission meeting.
What we know
- ๐ WhereOff Goshen Road near Mona, next to a solar farm, Unincorporated Juab County, Juab County
- ๐ข CompanyNebo North LLC (SetSquare Capital Group)
- ๐ณ Size361 acres
- โก Power it needs750 megawatts (about as much as 600,000 homes)
- ๐ Where the power comes fromRocky Mountain Power grid via the Mona power line; may also add gas power on site.
- ๐ง WaterTrucked-in water (source not stated)
- โ๏ธ Coolingclosed-loop
- ๐ต Cost$10 billion
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where will the water come from? ๐ I'll find out
- When will the site plan go before the county? ๐ I'll find out
- Which company will use the data centers? ๐ I'll find out
What happened so far
- April 15, 2026Juab County Planning Commission approved the conditional use permit.
- Sept 8, 2026Residents spoke against the project at the Juab County Commission meeting.
Local votes and rules
โ Approved
The county planning commission approved a conditional use permit for Nebo North LLC ('Project Nebo') to build a data center campus of about 3 million sq ft on county land just outside Mona. The public hearing lasted about four minutes and no residents came. Neighbors only learned of it months later. In September 2026 more than 100 residents protested at a county commission meeting; the commission chair said undoing the permit could bring costly lawsuits.
An aerial photo of the area.
Where this comes from
- Utahns left in the dark on $10B data center ยท The Salt Lake Tribune ยท Sept 14, 2026
- Mona citizens revolt against local data centers ยท Deseret News ยท Sept 8, 2026
- Nebo North Data Center Campus ยท More Than Just Parks ยท 2026