Approved, not built yet
DCPC data center north of Mona
Also called: Data Center Power Company Juab campus
A two-building data center (about 1 million square feet) planned north of Mona, with its own gas power. The county approved its permit and in November 2025 let it expand onto two more parcels.
Where things stand: Conditional use permit granted about late 2024; two more parcels added on Nov. 19, 2025.
๐ Latest update (Nov 19, 2025): Planning Commission approved two more permits so the buildings could cross onto adjacent parcels.
What we know
- ๐ WhereNorth of Mona (Section 5, Township 11 South, Range 1 East), Unincorporated Juab County, Juab County
- ๐ข CompanyData Center Power Company (DCPC)
- ๐ Where the power comes fromIsland power (made on site, with natural gas).
- ๐ผ New power linesNo
- ๐ง WaterLeased well water from a neighbor; may seek Central Utah Project water. About 300 acre-feet a year, per the developer.
- โ๏ธ Coolingclosed-loop
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will it use? ๐ I'll find out
- When will construction start? ๐ I'll find out
What happened so far
- Nov 20, 2024Juab County Planning Commission held a public hearing on DCPC's data center permit.
- Nov 19, 2025Planning Commission approved two more permits so the buildings could cross onto adjacent parcels.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Planning Commission Minutes, Nov. 19, 2025 ยท Juab County ยท Nov 19, 2025
- Public Hearing Notice: Conditional Use Permit made by DCPC ยท Juab County ยท Nov 2024
See something wrong? Tell us and we'll fix it.