ProposedBig (AI-size): 1,500 megawatts

Red Butte energy and data center campus (BrightNight)

Also called: Red Butte Data Center

BrightNight wants to build a 1.5 GW data center campus with solar, batteries and gas power in Iron County. Its application is on hold during the county's pause on data centers.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Iron County Commissioners (for land outside city and town limits).

Where things stand: Proposed Applied May 4, 2026; deemed incomplete May 22 and put on hold by the county's pause. The county ended the pause and adopted new data center rules on Oct. 26, 2026.

  • Oct 26, 2026: Unincorporated Iron County, Iron County: data center rules (ordinance) adopted Source

❓ 3 open questions about it: see below.

Last checked Nov 3, 2026.

🕒 Latest update (Oct 26, 2026): Iron County commissioners adopted new data center rules and repealed the county's pause on data center applications.

What we know

  • 📍 WhereAbout 20 miles from Cedar City, Unincorporated Iron County, Iron County
  • 🏢 CompanyBrightNight
  • 🌳 Size2,600 acres
  • ⚡ Power it needs1,500 megawatts (about as much as 1,200,000 homes)
  • 🔌 Where the power comes from300 MW solar, 300 MW batteries and 1.5 GW gas power on site (per the developer).

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the county's new rules allow the project when the pause ends? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
  • Has the developer filed a new or completed application under Iron County's new data center rules? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked public records for the exact site but found only a general area, so the map pin stays at the town or county.

    What happened so far

    • May 4, 2026
      BrightNight filed its application with Iron County.
    • May 22, 2026
      County found the application incomplete.
    • May 26, 2026
      Iron County adopted a 180-day pause on new data center applications; Red Butte is on hold.
    • Oct 12, 2026
      At a county hearing on new data center rules, BrightNight asked for standards based on measurable impacts and more flexibility. No vote was taken.
    • Oct 26, 2026
      Iron County commissioners adopted new data center rules and repealed the county's pause on data center applications.

    Local votes and rules

    📜 Data center rules

    Iron County commissioners unanimously adopted new rules for data centers and their power plants. Power plants that feed data centers must be at least half a mile from homes, hospitals, schools, day cares and care homes. Sites using more than 50,000 gallons of water a day must show the extra use will not harm the aquifer. There is no hard limit on water use. Data centers under 50 megawatts are treated differently from bigger ones.

    Oct 26, 2026

    ⏸️ Pause on new data centers

    In a separate vote the same day it adopted new data center rules, the Iron County Commission repealed its 180-day pause on data center, data center power plant and solar plant applications. The pause had been set to end Nov. 22, 2026.

    Oct 26, 2026

    📜 Data center rules

    Iron County commissioners held a public hearing on Oct. 12 on a new 'Strategic Development Zone' rule for large data centers and other big industry. They took no vote. The planning commission had recommended it without changes. One commissioner wants fewer limits and project-by-project deals. The county's pause ends Nov. 22; the commission meets again Oct. 26 and Nov. 9.

    Oct 12, 2026

    ⏸️ Pause on new data centers

    County commissioners passed an emergency 180-day pause on new applications for data centers, data center power plants and solar power plants (Ordinance 2026-13). It does not stop the Pronghorn 'Project Antelope' data center, whose application was already complete. It does pause BrightNight's Red Butte project. On August 10, 2026 the commission took up a change (Ordinance 2026-18) so the pause does not cover battery storage projects that already had a permit.

    May 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Proposed Data Center Information · Iron County · 2026
    2. Red Butte · BrightNight · 2026
    3. AI campus proposed in Iron County could bring 500 jobs · Cedar City News · 2026
    4. Iron County commissioners weigh changes to proposed data center ordinance as deadline approaches · St George News · Oct 12, 2026
    5. Iron County adopts new rules for data centers · The Salt Lake Tribune · Oct 27, 2026