Approved, not built yetBig (AI-size): 1,500 megawatts

Project Antelope data center west of Cedar City

Also called: Antelope Data Center

A big data center campus with its own gas power plant planned on 640 acres west of Cedar City. The county planning board approved it in June 2026, but residents appealed. A county pause on new data centers does not apply because the application was already complete.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Iron County Commissioners (for land outside city and town limits).

Where things stand: Approved, not built yet Planning Commission approved the permit June 4, 2026. Residents appealed; a hearing officer will decide.

  • Oct 26, 2026: Unincorporated Iron County, Iron County: data center rules (ordinance) adopted Source

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 4, 2026): Iron County Planning Commission unanimously approved the conditional use permit.

What we know

  • 📍 WhereAlong Antelope Springs Road, about 8 miles west of Iron Springs Road (all of Section 36, T34S, R14W; parcel E-0825-0000-0000), Unincorporated Iron County, Iron County
  • 🏢 CompanyPronghorn Development LLC
  • 🌳 Size640 acres
  • ⚡ Power it needs1,500 megawatts (about as much as 1,200,000 homes)
  • 🔌 Where the power comes fromIts own gas power plant (up to 1.5 GW) on site.
  • 🗼 New power linesNo
  • ❄️ Coolingclosed-loop
  • 👷 Jobs promised670

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When will the appeal be heard, and what did the hearing officer decide? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the planning commission agenda names parcel E-0825-0000-0000, all of Section 36, Township 34 South, Range 14 West. We placed the pin at the middle of that 640-acre parcel.

    What happened so far

    • June 2026
      Residents appealed the permit; a hearing officer will set the schedule.
    • June 4, 2026
      Iron County Planning Commission unanimously approved the conditional use permit.

    Local votes and rules

    📜 Data center rules

    Iron County commissioners unanimously adopted new rules for data centers and their power plants. Power plants that feed data centers must be at least half a mile from homes, hospitals, schools, day cares and care homes. Sites using more than 50,000 gallons of water a day must show the extra use will not harm the aquifer. There is no hard limit on water use. Data centers under 50 megawatts are treated differently from bigger ones.

    Oct 26, 2026

    ⏸️ Pause on new data centers

    In a separate vote the same day it adopted new data center rules, the Iron County Commission repealed its 180-day pause on data center, data center power plant and solar plant applications. The pause had been set to end Nov. 22, 2026.

    Oct 26, 2026

    📜 Data center rules

    Iron County commissioners held a public hearing on Oct. 12 on a new 'Strategic Development Zone' rule for large data centers and other big industry. They took no vote. The planning commission had recommended it without changes. One commissioner wants fewer limits and project-by-project deals. The county's pause ends Nov. 22; the commission meets again Oct. 26 and Nov. 9.

    Oct 12, 2026

    ✅ Approved

    The county planning commission unanimously approved a conditional use permit for Pronghorn Development's 'Project Antelope': up to five data center buildings (6.75 million sq ft) and a gas power plant of up to 1.5 gigawatts on about 640 acres along Antelope Springs Road, west of Cedar City. The permit has 62 conditions, including noise monitoring, water and dark-sky rules.

    June 4, 2026

    ⏸️ Pause on new data centers

    County commissioners passed an emergency 180-day pause on new applications for data centers, data center power plants and solar power plants (Ordinance 2026-13). It does not stop the Pronghorn 'Project Antelope' data center, whose application was already complete. It does pause BrightNight's Red Butte project. On August 10, 2026 the commission took up a change (Ordinance 2026-18) so the pause does not cover battery storage projects that already had a permit.

    May 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something