ProposedBig (AI-size): 9,000 acres

Project Beehive nuclear-powered data center near Price (Valar Atomics)

Also called: Project Beehive, Raceway Energy Campus

Valar Atomics wants data centers powered by gas and later by many small nuclear reactors near Price and Wellington. The first part, the Raceway Energy Campus on 640 acres of state land, got a county permit in Nov. 2026. A much bigger part on about 9,000 acres of federal land still needs federal review.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Carbon County Commissioners (for land outside city and town limits).

Where things stand: Proposed Nov. 12, 2026: county planning commission approved a permit for the first part (640 acres of state land near Wellington). The bigger federal (BLM) land part is still under review.

❓ 4 open questions about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Nov 12, 2026): Carbon County Planning Commission approved a conditional use permit for Valar Atomics' Raceway Energy Campus on about 640 acres of state trust land near Wellington, with one no vote. About 3 gigawatts, first powered by a gas plant, later 40 to 120 small reactors. It still needs a building permit, a state air permit and a federal nuclear permit.

What we know

  • 📍 WhereFederal and state land near Price, Unincorporated Carbon County, Carbon County
  • 🏢 CompanyValar Atomics
  • 🌳 Size9,000 acres
  • 🔌 Where the power comes fromUp to 456 small nuclear reactors (about 9.6 GW) on site.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When will the BLM open public comment on the federal land lease? 🙋 I'll find out ·
  • How big will the data centers be? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
  • How much water will the Raceway Energy Campus use, and where will it come from? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked public records for the exact site but found only a general area, so the map pin stays at the town or county.

    What happened so far

    • Sept 17, 2026
      Utah Trust Lands Administration board approved a lease of 640+ acres of state land.
    • Nov 12, 2026
      Carbon County Planning Commission approved a conditional use permit for Valar Atomics' Raceway Energy Campus on about 640 acres of state trust land near Wellington, with one no vote. About 3 gigawatts, first powered by a gas plant, later 40 to 120 small reactors. It still needs a building permit, a state air permit and a federal nuclear permit.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something