Built & running

xAI Colossus 2 campus on Tulane Road (Whitehaven)

Also called: Colossus 2

xAI's second Memphis supercomputer campus is on Tulane Road in Whitehaven, near the Mississippi line. It started running in January 2026 and xAI is adding a large new four-story building. Most of its power comes from gas turbines in nearby Southaven, Mississippi, which are the subject of legal fights over air pollution.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

Where things stand: Built & running First part came online in January 2026. In 2026 xAI filed a $659 million permit for another four-story building on the campus.

  • Oct 20, 2026: Memphis, Shelby County: moratorium decided Source

❓ 3 open questions about it: see below.

📣 Report noise, water or power bill changes

Last checked Oct 8, 2026.

🕒 Latest update (Jan 2026): Colossus 2 came online.

What we know

  • 📍 WhereTulane Road in Whitehaven, south Memphis; the new building is at 5414 Tulane Road (geocoded with the Census geocoder), Memphis, Shelby County
  • 🏢 CompanyxAI
  • 👤 Built forxAI (Grok chatbot)
  • 🌳 Size79 acres
  • 🔌 Where the power comes fromMostly gas turbines just across the state line in Southaven, Mississippi, plus grid power and Tesla Megapack batteries.
  • 💵 Cost$659 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts does Colossus 2 use from the Memphis grid? 🙋 I'll find out ·
  • How much water will the Tulane Road campus use per day? 🙋 I'll find out ·
  • Did xAI get any local tax breaks (PILOT) for Colossus 2? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the 2025 satellite picture. In 2018 this land east of Tulane Road was forest. By 2025 there is a very large new building and a cleared building site about 700 meters east of where our pin was. We moved the pin onto the new building.

    What happened so far

    • March 2025
      xAI bought the land for Colossus 2 on Tulane Road.
    • 2026
      xAI filed a $659 million building permit for a 312,000-square-foot, four-story building at 5414 Tulane Road.
    • Jan 2026
      Colossus 2 came online.

    Local votes and rules

    ⏸️ Pause on new data centers

    On the final vote, the proposed Memphis data center pause failed in a 6-6 tie, with one member absent. Reports differ on its length: some say 12 months, others say it had been changed to 18 months. The pause will not take effect in that form.

    Oct 20, 2026

    📜 Data center rules

    After the longer pause failed, the council passed a different measure. WSMV says it passed Ordinance 18, data center rules that ban most water-evaporating cooling, require closed-loop water systems and limit big local water withdrawals. CBS News says the council passed a substitute that halts data center building for 135 days. Reports do not make clear if these are the same measure.

    Oct 20, 2026

    📌 Other

    The Memphis City Council delayed its vote on a data center pause to Oct. 20 after a fight broke out and protests disrupted the meeting. Police cleared the room.

    Oct 6, 2026

    ⏸️ Pause on new data centers

    Memphis City Council is voting on a one-year pause on new data centers and AI or crypto computing sites. During the pause the city would not process rezonings, site plans or building permits for them. Existing data centers that do not expand are exempt. It passed the second of three votes unanimously on Sept. 1, 2026. The final vote was delayed twice; on Oct. 6 the council voted 7-5 to push it to Oct. 20, 2026.

    Sept 1, 2026

    ⚖️ Court case

    The Southern Environmental Law Center, for the NAACP and Young, Gifted & Green, appealed the Shelby County Health Department's air permit that lets xAI run 15 gas turbines at its South Memphis data center. They also object to how the department handled dozens of turbines that ran without a permit. We did not find a decision.

    July 16, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. xAI to invest $659 million in new Memphis data center cluster buildout for Grok · Construction Review Online · March 2026
    2. Sentinel-2 cloudless 2025 image of the Tulane Road site · EOX IT Services (Sentinel-2 cloudless) · Oct 8, 2026
    3. Sentinel-2 cloudless 2018 image of the Tulane Road site (before) · EOX IT Services (Sentinel-2 cloudless) · Oct 8, 2026