πŸ“£ Report Something
Status unclear

Connect Data Centers on South Mendenhall Road

Also called: Oppidan Memphis data center, Connect Memphis

Minnesota developer Oppidan filed plans in 2023 for a one-story, 99,000-square-foot data center on South Mendenhall Road in Memphis. It was supposed to open in 2025. It is marketed as Connect Data Centers.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Plans were filed in 2023 with a goal to open in 2025. We could not find an official or news source that says it is open.

πŸ•’ Latest update (May 2023): Oppidan filed with the Memphis and Shelby County Division of Planning and Development for a 99,000-square-foot, one-story data center.

What we know

  • πŸ“ Where3900 S. Mendenhall Road, southeast Memphis, Memphis, Shelby County
  • 🏒 CompanyOppidan

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 2023
    Oppidan filed with the Memphis and Shelby County Division of Planning and Development for a 99,000-square-foot, one-story data center.

Local votes and rules

⏸️ Pause on new data centers

Memphis City Council is voting on a one-year pause on new data centers and AI or crypto computing sites. During the pause the city would not process rezonings, site plans or building permits for them. Existing data centers that do not expand are exempt. It passed the second of three votes unanimously on Sept. 1, 2026. The final vote was delayed twice; on Oct. 6 the council voted 7-5 to push it to Oct. 20, 2026.

Sept 1, 2026

βš–οΈ Court case

The Southern Environmental Law Center, for the NAACP and Young, Gifted & Green, appealed the Shelby County Health Department's air permit that lets xAI run 15 gas turbines at its South Memphis data center. They also object to how the department handled dozens of turbines that ran without a permit. We did not find a decision.

July 16, 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.