Sequitor Edge data center in Rapid City

A smaller 'edge' data center planned in Rapid City's industrial park. It would start at 2 MW, about like a big store, and could grow. Reports differ on its full size (10 or 15 MW).

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 8, 2026

Where things stand: Announced Feb. 2026 for land already zoned industrial. Building permits still needed; construction not expected before late 2026.

๐Ÿ•’ Latest update (July 2, 2026): News report described it as a 15 MW data center; construction not expected until late 2026.

What we know

  • ๐Ÿ“ WhereBlack Hills Industrial Center, near Highway 79 on Rapid City's south side, Rapid City, Pennington County
  • ๐Ÿข CompanySequitor Edge
  • ๐ŸŒณ Size10 acres
  • โšก Power it needs2 megawatts (about as much as 1,600 homes)
  • ๐Ÿ”Œ Where the power comes fromBlack Hills Energy
  • โ„๏ธ CoolingClosed-loop cooling (one-time fill of about 20,000 gallons)
  • ๐Ÿ‘ท Jobs promised3

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Feb 12, 2026
    Sequitor Edge announced a 30,000 sq ft edge data center on 10 acres, starting at 2 MW and able to grow to 10 MW.
  • July 2, 2026
    News report described it as a 15 MW data center; construction not expected until late 2026.

Local votes and rules

๐Ÿ“œ Data center rules

Rapid City proposed data center rules (Ordinance 6746). The draft bans hyperscale data centers (50 MW or more, or over 10,000 gallons of water a day) in the city. Smaller ones would need distance from homes, a sound study, and non-water cooling. The Planning Commission put off its vote to Nov. 5, 2026. The city holds an open house on Oct. 14, 5-7:30 p.m., at City Hall.

Sept 10, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Sequitor Edge to Build Modular Data Center in Rapid City ยท KOTA Radio ยท Feb 12, 2026
  2. Heat raises resource concerns as Rapid City data center moves forward ยท KOTA Territory News ยท July 2, 2026

See something wrong? Tell us and we'll fix it.