๐Ÿ“ฃ Report Something
USA โ€บ South Dakota โ€บ Deuel County
Stopped or cancelled

Applied Digital AI campus near Toronto

Also called: Applied Digital Deuel County

Applied Digital, which runs big AI data centers in North Dakota, planned a large campus near Toronto. After state lawmakers turned down tax breaks, the company said it will not go ahead for now. It could come back later.

โœ” ConfirmedSourceLast checked: Oct 8, 2026

Where things stand: In April 2026 the company said the project 'doesn't make sense at this time' and it would let its land deal lapse.

๐Ÿ•’ Latest update (April 2, 2026): After lawmakers rejected tax breaks, the company said the $5 billion, 430 MW plan doesn't make sense now and it will let the land agreement lapse. It may look again after the elections.

What we know

  • ๐Ÿ“ Whererural land near the town of Toronto (exact site not public), unknown, Deuel County
  • ๐Ÿข CompanyApplied Digital
  • โšก Power it needs430 megawatts (about as much as 344,000 homes)
  • ๐Ÿ”Œ Where the power comes fromNear Otter Tail Power lines and the gas plant at Astoria
  • ๐Ÿ’ต Cost$5 billion
  • ๐Ÿ’ธ Tax breaksCompany said the project needed a state sales tax break on equipment. Lawmakers rejected it in 2025 and 2026.
  • ๐Ÿ‘ท Jobs promised200

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 2025
    Company said it wants to build near Toronto; total investment could top $16 billion with about 200 jobs, if the state passes a tax break.
  • April 2, 2026
    After lawmakers rejected tax breaks, the company said the $5 billion, 430 MW plan doesn't make sense now and it will let the land agreement lapse. It may look again after the elections.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. New AI data center wave could transform rural South Dakota, advocates say ยท SDPB ยท May 27, 2025
  2. One data center project 'unchanged' while another 'doesn't make sense' after rejected incentives ยท South Dakota Searchlight ยท April 2, 2026
  3. Deuel County no-go (republishes the South Dakota Searchlight article) ยท Bluestem Prairie ยท April 2, 2026

See something wrong? Tell us and we'll fix it.