Stopped or cancelled

TigerDC Project Spero data center

Also called: Project Spero, TigerDC SC1

TigerDC planned a $3 billion AI data center in the Tyger River Industrial Park, with its own gas power plant. After weeks of public opposition, County Council voted against its tax deal and the company pulled out.

✔ ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: TigerDC withdrew the project on Feb. 27, 2026, after County Council voted against its tax deal.

🕒 Latest update (Feb 27, 2026): County Council voted not to give the tax deal, and TigerDC withdrew the project.

What we know

  • 📍 WhereTyger River Industrial Park North, unknown, Spartanburg County
  • 🏢 CompanyTigerDC
  • ⚡ Power it needs100 megawatts (about as much as 80,000 homes)
  • 🔌 Where the power comes fromNatural gas power plant on site (developer's plan).
  • ❄️ Coolingclosed-loop water system (developer's claim)
  • 💵 Cost$3 billion
  • 👷 Jobs promised50

What happened so far

  • Nov 2025
    The tax deal for Project Spero passed first reading at Spartanburg County Council.
  • Jan 27, 2026
    TigerDC publicly announced the $3 billion Project Spero data center.
  • Feb 27, 2026
    County Council voted not to give the tax deal, and TigerDC withdrew the project.
🛰️ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. TigerDC announces $3 billion data center, new jobs in Spartanburg County · FOX Carolina · Jan 27, 2026
  2. Company withdraws AI data center from Spartanburg County consideration · FOX Carolina · Feb 27, 2026

See something wrong? Tell us and we'll fix it.