Proposed

NTT DATA new Hillsboro data center site (216 MW)

Also called: NTT Hillsboro expansion

NTT DATA, which already runs data centers in Hillsboro, bought more land in 2025 for about 216 more megawatts. The exact site and timeline have not been made public.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: NTT bought more land in Hillsboro in 2025; no public site plan found.

πŸ•’ Latest update (May 13, 2025): NTT DATA said it bought new land in Hillsboro, adding 216 MW for a planned total of 354 MW there.

What we know

  • πŸ“ WhereHillsboro, Washington County
  • 🏒 CompanyNTT DATA
  • πŸ›οΈ Owned byNTT
  • ⚑ Power it needs216 megawatts (about as much as 172,800 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 13, 2025
    NTT DATA said it bought new land in Hillsboro, adding 216 MW for a planned total of 354 MW there.

Local votes and rules

πŸ“œ Data center rules

Hillsboro is writing its first rules just for data centers and battery storage (Ordinance 6521, phase 1). The Planning Commission approved them on Sept. 9. They would keep data centers 1,000 feet from schools, allow standalone data centers only in two industrial zones with acreage caps, and require a public hearing for new ones. Council held a first reading Oct. 6; second reading is set for Oct. 20.

Oct 6, 2026

⏸️ Pause on new data centers

Hillsboro City Council voted unanimously to pause new land use applications for data centers and big battery storage sites for 120 days (Resolution 2932). Projects that applied before the vote can go ahead. The council can extend the pause for up to six more months.

July 27, 2026

βš–οΈ Court case

1000 Friends of Oregon, the Oregon Education Association, Tax Fairness Oregon and Tualatin Riverkeepers sued Hillsboro and Washington County. They say staff approved 17 data center tax break (enterprise zone) applications in a rush before the June 6 state deadline, without public notice or a vote by elected officials. The city and county say they followed the law.

June 22, 2026

🀝 Agreement with the company

Before a new state law paused data center tax breaks on June 6, 2026, Hillsboro and Washington County staff approved 17 enterprise zone tax break applications for data center projects. Companies named include Adobe, CoreWeave, Dropbox, Flexential and Nvidia. These approvals are now being challenged in court.

June 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.