Being built

Google's two new data centers at the former Northwest Aluminum site, The Dalles

Also called: Google The Dalles expansion, 3500 River Road

Google is adding two large data centers on the old Northwest Aluminum site in The Dalles. The city approved them in 2022 and 2024. Under a 20-year tax deal, Google pays $3 million per building plus yearly fees in place of most property taxes.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City approved both buildings (2022 and Jan. 2024). Trackers say they opened in 2025-26, not confirmed by Google.

๐Ÿ•’ Latest update (Jan 25, 2024): City approved the second new Google data center at the site.

What we know

  • ๐Ÿ“ Where3500 River Road, Port of The Dalles (former Northwest Aluminum site), The Dalles, Wasco County
  • ๐Ÿข CompanyDesign LLC (Google)
  • ๐Ÿ›๏ธ Owned byGoogle
  • ๐Ÿ‘ค Built forGoogle
  • ๐Ÿ’ธ Tax breaks20-year deal: $3 million up front per building, then community fees and reduced property taxes once built.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 2022
    Contractor Whiting-Turner applied to the city for a 290,000-square-foot Google data center at 3500 River Road.
  • Jan 25, 2024
    City approved the second new Google data center at the site.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Google making moves to break ground on first new data center in The Dalles ยท Columbia Community Connection ยท Sept 20, 2022
  2. Google gets another go: second data center garners TD city approval ยท Columbia Community Connection ยท Jan 25, 2024

See something wrong? Tell us and we'll fix it.