Being builtBig (AI-size): 400 acres

Google data center campus at Perkins and Richmond roads (Stillwater)

Also called: Google Stillwater campus

Google is building a data center campus on about 400 acres at Perkins and Richmond roads in Stillwater. Plans call for up to six large buildings over about 25 years. The city says it is worth about $3 billion.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Stillwater City.

Where things stand: Being built Final plat approved Nov 2025 and building permits issued for the first two lots. First building expected about 2027.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Nov 18, 2025): Planning Commission voted 4-0 to approve the final plat for 202 acres (three lots); permits for lots 1 and 2 already approved.

What we know

  • 📍 WhereSouth side of Richmond Rd between Perkins Rd and Jardot Rd, north Stillwater, Stillwater, Payne County
  • 🏢 CompanyGoogle
  • 🏛️ Owned byAlphabet
  • 👤 Built forGoogle
  • 🌳 Size400 acres
  • 💵 Cost$3 billion
  • 💸 Tax breaksGoogle makes payments in lieu of taxes under a city agreement instead of paying regular property taxes at first.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water and power will the Stillwater campus use? 🙋 I'll find out ·
  • What exactly does Google pay the city and schools instead of property taxes? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: news reports put the campus at Perkins and Richmond roads, with Richmond Road to be paved from Perkins Road to Jardot Road. Recent satellite images show a large construction site south of Richmond Road between those two roads. The pin is in the middle of it.

    What happened so far

    • March 12, 2025
      Stillwater said Google is the company behind the planned data center campus.
    • Nov 18, 2025
      Planning Commission voted 4-0 to approve the final plat for 202 acres (three lots); permits for lots 1 and 2 already approved.

    Local votes and rules

    ✅ Approved

    Stillwater's Planning Commission voted 4-0 to approve the final plat (lot layout) for 202 acres of the Google data center campus, in three lots. Permits for two lots were already approved.

    Nov 18, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Google will operate massive data center development in Stillwater · KGOU · March 13, 2025
    2. Stillwater data center final plat approved by planning commission · Southwest Ledger · Nov 2025
    3. Where are data centers being built across Oklahoma? · News 9 · June 10, 2026