Black Bear AI data center campus (Oklahoma AI Ventures, near Morrison)
Also called: Black Bear AI
Oklahoma AI Ventures wants to build a data center campus called Black Bear AI near Morrison in western Pawnee County. It is very early: officials have met with the developer and allowed a power study, but no zoning request, size or user has been made public.
What happens next?
🗓️ No meeting or deadline known yet.
Where things stand: Proposed Early stage. In Nov 2026 the City of Pawnee allowed a study of how the campus would connect to the power grid. No zoning or permits found.
- Nov 6, 2026: Pawnee, Pawnee County: agreement adopted Source
❓ 5 open questions about it: see below.
Last checked Nov 15, 2026.
🕒 Latest update (Nov 6, 2026): Pawnee City Council let the mayor sign an authorization so the Grand River Dam Authority can study connecting the Black Bear AI campus to the power grid. The developer pays for the study, and Oklahoma State University is doing a separate study on local effects.
What we know
- 📍 Wherewestern Pawnee County, near Morrison (no exact site published), Pawnee County
- 🏢 CompanyOklahoma AI Ventures, LLC
- 🏛️ Owned byJoint venture of Comstock Holding Companies and Jericho Energy Ventures (per company announcement)
- 🔌 Where the power comes fromGrand River Dam Authority is studying a grid connection; the City of Pawnee could sell the power if the project goes ahead.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Where exactly is the site, and is it in Pawnee County or Noble County? Morrison itself is in Noble County. A parcel number or address helps. 🙋 I'll find out ·
- How many acres and megawatts would the campus use? 🙋 I'll find out ·
- Where would its water come from, and how much would it use per day? 🙋 I'll find out ·
- Which company would use the data center? 🙋 I'll find out ·
- Did the city or county sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
What happened so far
- June 10, 2026Comstock and Jericho Energy Ventures announced a joint venture, Oklahoma AI Ventures, to build large data center campuses in Pawnee and Noble counties.
- Nov 6, 2026Pawnee City Council let the mayor sign an authorization so the Grand River Dam Authority can study connecting the Black Bear AI campus to the power grid. The developer pays for the study, and Oklahoma State University is doing a separate study on local effects.
Local votes and rules
🤝 Agreement with the company
Pawnee City Council let the mayor sign a limited authorization so the Grand River Dam Authority can study, with the developer Oklahoma AI Ventures and the Southwest Power Pool, how a proposed data center campus near Morrison could connect to the power grid. The developer pays for the study. The city said this was its only action on the project so far.
Drag the slider to compare the land before and now.
Where this comes from
- Pawnee, county officials meet with developers over potential data center project · KTUL · Nov 10, 2026
- Comstock and Jericho form Oklahoma data center joint venture (summary of company press release) · BriefGlance · June 10, 2026