Send us a tip
Being builtBig (AI-size): 200 megawatts

CloudBurst data center campus on S Council Road (Oklahoma City)

Also called: CloudBurst Oklahoma City Campus

CloudBurst is building three data centers on S Council Road in southwest Oklahoma City, adding up to 200 megawatts in phases through 2028.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Oklahoma City City.

Where things stand: Being built Ground broke end of 2025; first 30 MW expected end of 2026, full 200 MW by end of 2028.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Dec 2025): CloudBurst broke ground on the campus.

What we know

  • 📍 Where2000 S Council Rd, near SW 29th St, southwest Oklahoma City, Oklahoma City, Oklahoma County
  • 🏢 CompanyCloudBurst Data Centers
  • ⚡ Power it needs200 megawatts (about as much as 160,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where will the power come from, and will there be on-site generators? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site pin on a satellite image: a large existing building on S Council Rd is at the pin.

    What happened so far

    • Dec 2025
      CloudBurst broke ground on the campus.

    Local votes and rules

    ⏸️ Pause on new data centers

    City Council voted unanimously to extend its pause on new data center applications and rezoning requests through the end of 2027, or until the city updates its zoning code, whichever comes first. The new rules also make exceptions for some pending rezoning requests and set up a way to appeal. It took effect right away.

    Nov 10, 2026

    ✅ Approved

    City Council voted 6-3 to rezone two tracts near I-40 and Frisco Road (3025 N. Frisco Road and NW 23rd Street) for Beltline Energy's data center campus. Conditions cover water, power and noise; the noise cap was lowered to 55 decibels. A community benefits agreement is needed before any building permit. The request was filed before the city's data center pause.

    Oct 27, 2026

    ⏸️ Pause on new data centers

    City Council voted 7-2 to narrow its data center pause. It now covers only large data centers that use more than 75 megawatts of power. Sites at the Expand Energy campus and near the OKC Outlet Mall were also exempted.

    May 19, 2026

    ⏸️ Pause on new data centers

    Oklahoma City Council voted unanimously to stop taking new applications, rezonings and building permits for data centers until December 31, 2026, or sooner if the city adopts data center zoning rules. Two pending data center rezoning cases were left out of the pause, and owners can appeal.

    April 21, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. CloudBurst data center campus in OKC · News 9 · Sept 14, 2026
    2. Where are data centers being built across Oklahoma? · News 9 · June 10, 2026
    3. USGS imagery of 2000 S Council Rd · USGS The National Map · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.