Project Astralus data center and gas power plant (Yellow Creek Township)
Also called: Zuharis data center
A company called Zuharis plans an AI data center with its own power plant on about 510 acres in Yellow Creek Township. It says the first 500 megawatts could open in 2027, with another 500 after that. It would take water from the Ohio River. Many residents who came to the meeting were against it.
Where things stand: Company held a public meeting in May 2026 and says it has its permits. Building was planned to start in fall 2026.
🕒 Latest update (May 2026): Zuharis held a public meeting at the Highlandtown fire station. About 100 people came.
What we know
- 📍 WhereAbout 510 acres near the Columbiana–Jefferson County line, with its own exit off State Route 7, Yellow Creek, Columbiana County
- 🏢 CompanyZuharis
- 🌳 Size510 acres
- ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)
- 🔌 Where the power comes fromIts own power plant on site, not connected to the grid, per the company
- 💧 WaterOwn intake on the Ohio River, with Buckeye Water District
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which state permits (air, water) has the power plant received? 🙋 I'll find out
- How much river water would the site take each day? 🙋 I'll find out
- Is there a tax agreement with the county or schools? 🙋 I'll find out
What happened so far
- May 2026Zuharis held a public meeting at the Highlandtown fire station. About 100 people came.
🛰️ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Public information meeting held for data center in Yellow Creek Township · Salem News · May 2026
- Data center plan moves forward in Yellow Creek Twp · WFMJ · May 2026
See something wrong? Tell us and we'll fix it.