Approved, not built yetBig (AI-size): 471 acres

Amazon (AWS) data center campus in southwest Wilmington

Amazon wants to build a $4 billion data center campus on 471 acres in southwest Wilmington. The first phase would have three buildings, a substation and a water treatment plant. The city rezoned the land in September 2026 by emergency vote.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Wilmington City.

Where things stand: Approved, not built yet City Council passed the rezoning 7-0 on Sept. 3, 2026, as an emergency law. Residents are still objecting.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Sept 3, 2026): City Council passed the rezoning from rural residential to light industrial 7-0 as an emergency law, after it failed 5-2 two weeks earlier.

What we know

  • 📍 WhereOff U.S. 68, near the Timber Glen neighborhood in southwest Wilmington, Wilmington, Clinton County
  • 🏢 CompanyAmazon Web Services
  • 👤 Built forAmazon
  • 🌳 Size471 acres
  • 🔌 Where the power comes fromAES Ohio
  • 💧 WaterCity of Wilmington (Amazon would pay residential rates plus a reserve fee)
  • 💵 Cost$4 billion
  • 💸 Tax breaksProposed 30-year deal: from 2035 to 2064 Amazon would pay 30% of normal property taxes to the city, schools, Laurel Oaks career campus and the port authority.
  • 👷 Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did City Council give final approval to the 30-year tax break? 🙋 I'll find out ·
  • How much water will the campus use each day? 🙋 I'll find out ·
  • Has the Planning Commission approved the site plan? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 2, 2025
      City Council took up a 30-year tax break for a $4 billion Amazon data center after delaying the vote twice.
    • Jan 8, 2026
      Planning Commission tabled the site plan because water and habitat studies were missing.
    • Sept 3, 2026
      City Council passed the rezoning from rural residential to light industrial 7-0 as an emergency law, after it failed 5-2 two weeks earlier.

    Local votes and rules

    🗳️ Public vote

    Voters overturned, by about 80%, four city rezonings of rural land to light industrial (about 550 acres) passed for data centers. The referendum targeted the rezoning for the Ardent/TAC data center plan, not the separate Amazon rezoning. Our earlier record linked it to Amazon by mistake. Results are unofficial until the county elections board certifies them (expected in late November 2026).

    Nov 3, 2026

    🗳️ Public vote

    Voters will decide four referendums that could strike down zoning ordinances the city passed for the planned Amazon Web Services data center. A separate citizen zoning ordinance was kept off the ballot by the county elections board, and its backers went to the Ohio Supreme Court.

    Nov 3, 2026

    🗺️ Zoning change

    City council passed emergency rezoning that clears the way for a 1.9-million-square-foot Amazon Web Services data center on 471 acres along South U.S. 68. Emergency laws take effect right away and cannot be put to a referendum.

    Sept 3, 2026

    ⚖️ Court case

    A resident sued to overturn the 'emergency' rezoning for the Amazon data center, saying the emergency label was used to block a public vote.

    Sept 2026

    ✋ Turned down

    City council re-passed the generator noise rule 6-1 as an emergency, but the rezoning for the Amazon Web Services data center failed because it needed at least 75% of the vote.

    Aug 20, 2026

    ⚖️ Court case

    A federal judge ruled that Wilmington did not give proper public notice before passing zoning, data center use and generator noise rules for a planned $4 billion Amazon Web Services data center. The city had to redo them before acting on the site plan.

    July 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something