Sentinel data center campus near West Jefferson

Sentinel Data Centers plans three two-story data center buildings on about 79 acres next to West Jefferson. It says it will cost $1.5 billion, use air cooling, and take up to 15 years to finish.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Trustees of Deer Creek Township.

Where things stand: Status unclear West Jefferson approved a pre-annexation agreement for 78.83 acres. Two data center trackers now list the project as canceled or withdrawn; we found no news report saying so.

❓ 4 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (2026): West Jefferson Village Council approved a pre-annexation agreement with Sentinel Data Centers for 78.83 acres.

What we know

  • 📍 Where78.83 acres just outside the Village of West Jefferson, to be annexed into the village, Deer Creek, Madison County
  • 🏢 CompanySentinel Data Centers
  • 🌳 Size79 acres
  • 🔌 Where the power comes fromOhio Edison is studying the power load.
  • ❄️ CoolingAir cooling (developer says no large water demand)
  • 💵 Cost$1.5 billion
  • 💸 Tax breaksDeveloper plans to ask for a 15-year property tax break and sales tax exemptions on equipment.
  • 👷 Jobs promised250

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has the land been annexed into West Jefferson yet? 🙋 I'll find out ·
  • How many megawatts will the campus need? 🙋 I'll find out ·
  • Will the village approve the tax breaks? 🙋 I'll find out ·
  • Is the Sentinel project near West Jefferson still going ahead, or was it canceled? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2026
      West Jefferson Village Council approved a pre-annexation agreement with Sentinel Data Centers for 78.83 acres.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. New York developer advances USD 1.5bn hyperscale campus in Central Ohio · New Project Media · 2026
    2. Sentinel Data Centers West Jefferson Project (tracker listing) · More Than Just Parks Data Center Tracker · Oct 22, 2025

    See something wrong? Tell us and we'll fix it.