ProposedBig (AI-size): 750 megawatts

Bitdeer AI data center at Turnpike Commerce Center (Shalersville)

Also called: Bitdeer Shalersville Data Center

Bitdeer and local developer Geis want to build 15 data center buildings on 257 acres near the Turnpike. It would start at 150 megawatts and grow to 750. The company says it would use under 3,000 gallons of water a day in phase 1. Many residents oppose it, and the township is working on new zoning rules.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Trustees of Shalersville Township.

Where things stand: Proposed Township pause on data centers ends in early November 2026. Township is weighing zoning changes; no application approved.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Aug 12, 2026): Portage County Regional Planning Commission tabled the township's proposed zoning changes on data centers.

What we know

  • 📍 WhereTurnpike Commerce Center near the Ohio Turnpike interchange, Beck Road, Shalersville, Portage County
  • 🏢 CompanyShalersville Holdings (Geis Companies) and Bitdeer Technologies
  • 🏛️ Owned byBitdeer Technologies Group
  • 🌳 Size257 acres
  • ⚡ Power it needs750 megawatts (about as much as 600,000 homes)
  • 💧 Water3,000 gallons a day
  • ❄️ CoolingClosed loop, per the company
  • 💸 Tax breaksCompany says it will not take any tax breaks.
  • 👷 Jobs promised200

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the township make its data center pause permanent or adopt new zoning before November 2026? 🙋 I'll find out ·
  • Is the 3,000 gallons a day for one building or the whole campus? 🙋 I'll find out ·
  • Where would the power come from, and would new power lines be needed? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • May 30, 2026
      Geis and Bitdeer held an open house; protesters gathered outside.
    • Aug 12, 2026
      Portage County Regional Planning Commission tabled the township's proposed zoning changes on data centers.

    Local votes and rules

    ⏸️ Pause on new data centers

    Township trustees passed a six-month pause (moratorium) on new data centers, then extended it. It is set to end in November 2026.

    Nov 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Shalersville residents speak out against opposed data center (Record-Courier) · Record-Courier via AOL · June 1, 2026
    2. Shalersville weighs zoning changes to block data center · The Portager · Aug 14, 2026
    3. OpenStreetMap Nominatim result for Beck Road, Shalersville · OpenStreetMap contributors · Oct 7, 2026
    4. Bitdeer Shalersville Building 1 · Data Center Map · 2026

    See something wrong? Tell us and we'll fix it.