Unnamed data center developer seeking land (Scioto Township, Jackson County)

Farm owners in Scioto Township got offers from an unnamed company to buy land for a data center. No plan has been made public. The township has no zoning, so residents started writing a zoning code that voters must approve.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Trustees of Scioto Township.

Where things stand: Proposed Landowners got offers in early 2026. No company or plan made public. The township started writing zoning rules.

❓ 2 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (May 2026): Township trustees appointed a zoning commission to write the township's first zoning code.

What we know

  • 📍 WhereScioto, Jackson County

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company is buying land, and how big would the data center be? 🙋 I'll find out ·
  • When will township voters decide on zoning? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Feb 2026
      Landowners received offers to sell land for a data center.
    • March 2026
      Over 200 people met at the Scioto Township fire station about the possible data center.
    • May 2026
      Township trustees appointed a zoning commission to write the township's first zoning code.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data centers could spark change for zoning in Ohio's rural areas · WOUB Public Media · March 30, 2026
    2. Facing data center, Jackson County township moves forward with zoning · WOUB Public Media · June 4, 2026

    See something wrong? Tell us and we'll fix it.