Province Group data center campus at Champion Farm (Perry Village)
Also called: Champion Farm site
California-based Province Group plans about six data center buildings, each about 250,000 square feet, on about 230 acres the village and township agreed to sell. That is about one-sixth of the village. The mayor says it would bring tax money; many residents want more answers first.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Village Board of Perry Village.
Where things stand: Proposed Land is under contract; no site plan filed yet. A village data center pause in 2026 leaves out this site.
- Nov 3, 2026: Perry, Lake County: referendum decided Source
❓ 4 open questions about it: see below.
Last checked Nov 9, 2026.
🕒 Latest update (Nov 3, 2026): Perry voters approved, with more than 87% yes, a law requiring very large data centers that seek tax breaks to post a bond backing promised taxes and jobs (unofficial results).
What we know
- 📍 WhereFormer nursery land off Route 20 in the center of the village, next to the public library, Perry, Lake County
- 🏢 CompanyProvince Group
- 🌳 Size230 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power and water would the campus need? 🙋 I'll find out ·
- Will Province Group ask for tax breaks, and will schools get payments? 🙋 I'll find out ·
- Who would use the data center? 🙋 I'll find out ·
- Will Province Group seek tax breaks under Perry's new bond rule? 🙋 I'll find out ·
What happened so far
- July 2024A Province Group company agreed to buy 163 acres from the village for $8.4 million, plus land from Perry Township and the Perry JEDD.
- June 12, 2025Village council held a hearing on adding data centers as a permitted use in the industrial district.
- April 9, 2026Residents protested at a packed council meeting.
- Sept 10, 2026Council held a second reading of a one-year data center pause that leaves out the Champion Farm site.
- Nov 3, 2026Perry voters approved, with more than 87% yes, a law requiring very large data centers that seek tax breaks to post a bond backing promised taxes and jobs (unofficial results).
Local votes and rules
🗳️ Public vote
Voters approved, with more than 87% yes, a law that makes very large data centers seeking village tax breaks first post a bond backing the taxes and jobs they promise. It also sets noise limits. Results are unofficial until the county elections board certifies them (expected in late November 2026).
🗳️ Public vote
Voters will decide a proposal that would make any very large (hyperscale) data center seeking village tax breaks first give enforceable financial guarantees.
⏸️ Pause on new data centers
Village council is considering a one-year pause (moratorium) on new data centers.
Drag the slider to compare the land before and now.
Where this comes from
- Crowd packs Perry Village hall to protest 200-plus-acre data-center campus · News 5 Cleveland · April 10, 2026
- Perry Village residents demand answers on proposed data center · Cleveland 19 · April 14, 2026
- Perry Village Council regular meeting agenda, Sept. 10, 2026 · Village of Perry · Sept 10, 2026
- Data centers go 0-for-21 in ballot initiatives around Ohio · Ohio Capital Journal · Nov 9, 2026
- Ohioans overwhelmingly oppose data centers. 21 ballot measures just put their ire to the test · Fortune · Nov 4, 2026
See something wrong? Tell us and we'll fix it.