In 2024 Microsoft looked at building up to six data center buildings on about 350 acres in Perry Township, south of Lima. Two months later it dropped the site.
Where things stand: Microsoft dropped the site on Oct. 16, 2024, about two months after announcing it.
๐ Latest update (Oct 16, 2024): Microsoft said it would not pursue the Breese Road site.
What we know
- ๐ WhereAbout 350 acres on Breese Road, east of State Route 65, Perry, Allen County
- ๐ข CompanyMicrosoft
- ๐ค Built forMicrosoft
- ๐ณ Size350 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is anyone else now planning a data center on the Breese Road land? ๐ I'll find out
What happened so far
- Aug 12, 2024Microsoft said it was studying a data center campus of up to six buildings on about 350 acres in Perry Township.
- Oct 16, 2024Microsoft said it would not pursue the Breese Road site.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Exploring the potential to expand our presence in Ohio ยท Microsoft ยท Oct 16, 2024
See something wrong? Tell us and we'll fix it.