Mt. Orab mega site (possible data center)
Also called: DB Stu LLC
A company called DB Stu LLC bought about 1,000 acres around Mt. Orab and asked the power grid for 2,000 megawatts, the size of a giant data center. Officials signed agreements to keep plans private (NDAs). Residents pushed for a pause, and the village passed one.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Village Board of Mount Orab Village.
Where things stand: Status unclear The developer bought about 1,018 acres and asked the grid for 2,000 megawatts, but has not filed plans saying what it will build. The village moved to pause data center permits.
❓ 3 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (June 2026): News reports listed Mt. Orab among places that enacted a data center moratorium.
What we know
- 📍 WhereNear the village center, bordered by Oakland Road, New Hope-White Oak Station Road and Tri-County Highway, Mount Orab, Brown County
- 🏢 CompanyDB Stu LLC
- 🌳 Size1,018 acres
- ⚡ Power it needs2,000 megawatts (about as much as 1,600,000 homes)
- 🤐 Privacy agreement (NDA)Yes. Village council members signed agreements with the developer to keep plans private (NDAs). One member later took his back.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is behind DB Stu LLC, and is it a data center? 🙋 I'll find out ·
- What does the privacy agreement (NDA) with village officials say? 🙋 I'll find out ·
- When does the Mt. Orab moratorium end? 🙋 I'll find out ·
What happened so far
- Feb 3, 2026A council member introduced a 180-day pause on data center permits in Mt. Orab; it passed first reading.
- June 2026News reports listed Mt. Orab among places that enacted a data center moratorium.
Local votes and rules
⏸️ Pause on new data centers
Village council passed a 180-day (about six months) pause (moratorium) on new data centers. It is set to end in February 2027.
Drag the slider to compare the land before and now.
Where this comes from
- Mt. Orab council introduces data center moratorium amid community opposition to mysterious mega site project · WCPO · Feb 2026
- Butler County Commissioners approve short-term data center moratorium · WYSU · June 17, 2026
- OpenStreetMap road junction check · OpenStreetMap contributors · Oct 7, 2026
- OpenStreetMap road junction check · OpenStreetMap contributors · Oct 7, 2026
See something wrong? Tell us and we'll fix it.