Status unclearBig (AI-size): 2,000 megawatts

Mt. Orab mega site (possible data center)

Also called: DB Stu LLC

A company called DB Stu LLC bought about 1,000 acres around Mt. Orab and asked the power grid for 2,000 megawatts, the size of a giant data center. Officials signed agreements to keep plans private (NDAs). Residents pushed for a pause, and the village passed one.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Village Board of Mount Orab Village.

Where things stand: Status unclear The developer bought about 1,018 acres and asked the grid for 2,000 megawatts, but has not filed plans saying what it will build. The village moved to pause data center permits.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (June 2026): News reports listed Mt. Orab among places that enacted a data center moratorium.

What we know

  • 📍 WhereNear the village center, bordered by Oakland Road, New Hope-White Oak Station Road and Tri-County Highway, Mount Orab, Brown County
  • 🏢 CompanyDB Stu LLC
  • 🌳 Size1,018 acres
  • ⚡ Power it needs2,000 megawatts (about as much as 1,600,000 homes)
  • 🤐 Privacy agreement (NDA)Yes. Village council members signed agreements with the developer to keep plans private (NDAs). One member later took his back.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is behind DB Stu LLC, and is it a data center? 🙋 I'll find out ·
  • What does the privacy agreement (NDA) with village officials say? 🙋 I'll find out ·
  • When does the Mt. Orab moratorium end? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Feb 3, 2026
      A council member introduced a 180-day pause on data center permits in Mt. Orab; it passed first reading.
    • June 2026
      News reports listed Mt. Orab among places that enacted a data center moratorium.

    Local votes and rules

    ⏸️ Pause on new data centers

    Village council passed a 180-day (about six months) pause (moratorium) on new data centers. It is set to end in February 2027.

    Aug 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Mt. Orab council introduces data center moratorium amid community opposition to mysterious mega site project · WCPO · Feb 2026
    2. Butler County Commissioners approve short-term data center moratorium · WYSU · June 17, 2026
    3. OpenStreetMap road junction check · OpenStreetMap contributors · Oct 7, 2026
    4. OpenStreetMap road junction check · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.