Decimal Digital AI data center idea (Monroeville)
Decimal Digital wants to use another property in Monroeville for an AI data center. It says the technology is different from the noisy bitcoin mine in the village. The village is drafting rules for noise, setbacks and generators.
Where things stand: Only a pitch. The village was writing data center zoning rules and considering an advisory vote.
π Latest update (Aug 15, 2026): Decimal Digital planned a public information event at Monroeville's American Legion post.
What we know
- π WhereMonroeville, Huron County
- π’ CompanyDecimal Digital
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which property would be used, and how big would the data center be? π I'll find out
- Will Monroeville hold an advisory vote on data centers? π I'll find out
What happened so far
- Aug 15, 2026Decimal Digital planned a public information event at Monroeville's American Legion post.
Local votes and rules
π Other
Voters will answer a non-binding (advisory) question to tell village council whether they support data centers. A data center is proposed in the village.
βΈοΈ Pause on new data centers
Village council passed a one-year pause (moratorium) on new data centers. It is set to end in February 2027.
An aerial photo of the area.
Where this comes from
- Ohio village welcomed a bitcoin mine, then got noise and a fight over $1.3 million (citing the Norwalk Reflector) Β· The Cool Down Β· July 11, 2026
See something wrong? Tell us and we'll fix it.