Vantage Data Centers campus and Fairfield Energy Center (Millersport)
Also called: Vantage Millersport Campus, Vantage OH2, Fairfield Energy Center
Vantage is building a $2.1 billion campus of four data centers on farmland annexed into Millersport. A separate company wants to build a gas power plant of up to 1,300 megawatts next door to run it. Vantage says the campus will use about 5.5 million gallons of water a year. Neighbors worry about air pollution and secrecy.
Where things stand: Construction began May 2026. The 1,300 MW gas power plant to run it still needs state approval.
๐ Latest update (Aug 17, 2026): Ohio Power Siting Board public hearing on the Fairfield Energy Center at Millersport Junior/Senior High School (case 26-160-EL-BGN).
What we know
- ๐ WhereOff State Routes 204 and 37; land annexed from Walnut Township in 2025, Millersport, Fairfield County
- ๐ข CompanyVantage Data Centers
- ๐ณ Size350 acres
- ๐ Where the power comes fromPlanned gas-fired Fairfield Energy Center on 100 acres next to the site (up to 1,300 MW plus up to 1,000 MW of batteries), built by Advanced Power on land leased from Vantage
- ๐ง Water15,000 gallons a day
- โ๏ธ CoolingClosed-loop cooling, per the company
- ๐ต Cost$2.1 billion
- ๐ธ Tax breaksState gave a 50% sales tax exemption for 10 years on some purchases.
- ๐ท Jobs promised50
- ๐ค Secret deal (NDA)Yes. Residents told regulators public officials signed an NDA with Vantage; the agreement itself was not published.
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will the Ohio Power Siting Board approve the Fairfield Energy Center? ๐ I'll find out
- Was a secret deal (NDA) signed with local officials, and can it be released? ๐ I'll find out
- How many megawatts will the data centers use? ๐ I'll find out
What happened so far
- May 2025Fairfield County commissioners approved annexing 500 acres from Walnut Township into Millersport for a data center.
- Sept 2025An earlier 'Millersport Energy Center' power plant application was withdrawn.
- Oct 2025The state confirmed Vantage's $2.1 billion project and a 10-year, 50% sales tax exemption.
- May 2026Construction began.
- Aug 17, 2026Ohio Power Siting Board public hearing on the Fairfield Energy Center at Millersport Junior/Senior High School (case 26-160-EL-BGN).
Drag the slider to compare the land before and now.
Where this comes from
- Some residents hesitant about new $1 billion data center headed for central Ohio ยท NBC4 WCMH ยท June 24, 2025
- $2.1 billion Vantage data center announced for Fairfield County ยท NBC4 WCMH ยท Oct 2025
- Fairfield County, Ohio data center draws skepticism, alternative utility plans ยท NBC4 WCMH via WKBN ยท Aug 12, 2026
- OPSB schedules local hearings for 2 proposed natural gas plants to power data centers ยท Farm and Dairy ยท July 19, 2026