Being builtBig (AI-size): 350 acres

Vantage Data Centers campus and Fairfield Energy Center (Millersport)

Also called: Vantage Millersport Campus, Vantage OH2, Fairfield Energy Center

Vantage is building a $2.1 billion campus of four data centers on farmland annexed into Millersport. A separate company wants to build a gas power plant of up to 1,300 megawatts next door to run it. Vantage says the campus will use about 5.5 million gallons of water a year. Neighbors worry about air pollution and secrecy.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Village Board of Millersport Village.

Where things stand: Being built Construction began May 2026. The 1,300 MW gas power plant to run it still needs state approval.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 17, 2026): Ohio Power Siting Board public hearing on the Fairfield Energy Center at Millersport Junior/Senior High School (case 26-160-EL-BGN).

What we know

  • 📍 WhereOff State Routes 204 and 37; land annexed from Walnut Township in 2025, Millersport, Fairfield County
  • 🏢 CompanyVantage Data Centers
  • 🌳 Size350 acres
  • 🔌 Where the power comes fromPlanned gas-fired Fairfield Energy Center on 100 acres next to the site (up to 1,300 MW plus up to 1,000 MW of batteries), built by Advanced Power on land leased from Vantage
  • 💧 Water15,000 gallons a day
  • ❄️ CoolingClosed-loop cooling, per the company
  • 💵 Cost$2.1 billion
  • 💸 Tax breaksState gave a 50% sales tax exemption for 10 years on some purchases.
  • 👷 Jobs promised50
  • 🤐 Privacy agreement (NDA)Yes. Residents told regulators public officials signed an NDA with Vantage; the agreement itself was not published.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the Ohio Power Siting Board approve the Fairfield Energy Center? 🙋 I'll find out ·
  • Did local officials sign an agreement to keep the plans private (NDA), and can it be released? 🙋 I'll find out ·
  • How many megawatts will the data centers use? 🙋 I'll find out ·
  • What are the parcel numbers of the land annexed into Millersport for the Vantage campus? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • May 2025
      Fairfield County commissioners approved annexing 500 acres from Walnut Township into Millersport for a data center.
    • Sept 2025
      An earlier 'Millersport Energy Center' power plant application was withdrawn.
    • Oct 2025
      The state confirmed Vantage's $2.1 billion project and a 10-year, 50% sales tax exemption.
    • May 2026
      Construction began.
    • Aug 17, 2026
      Ohio Power Siting Board public hearing on the Fairfield Energy Center at Millersport Junior/Senior High School (case 26-160-EL-BGN).
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.