๐Ÿ“ฃ Report Something
USA โ€บ Ohio โ€บ Wood County โ€บ Middleton Township
Being built

Meta data center in Middleton Township (Wood County)

Also called: Liames LLC

Meta is building an $800 million data center on 280 acres in Middleton Township, between Perrysburg and Bowling Green. It started under the shell name Liames LLC. Meta says about 100 people will work there.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Under construction since 2025. In 2026 Meta asked to rezone about 32 more acres around the site for construction use.

๐Ÿ•’ Latest update (May 28, 2026): A request was filed to rezone 13 more parcels (about 32 acres) owned by Meta for construction use.

What we know

  • ๐Ÿ“ WhereNear I-75 and State Route 582, bordered by Ohio 582, Ohio 25 and Mercer Road, between Perrysburg and Bowling Green, Middleton, Wood County
  • ๐Ÿข CompanyLiames LLC (Meta)
  • ๐Ÿ›๏ธ Owned byMeta Platforms
  • ๐Ÿ‘ค Built forMeta
  • ๐ŸŒณ Size280 acres
  • ๐Ÿ”Œ Where the power comes fromMeta says it will match the site's power use with 100% clean and renewable energy.
  • ๐Ÿ’ต Cost$800 million
  • ๐Ÿ’ธ Tax breaksMeta will pay Eastwood Schools $900,000 a year for 15 years, starting after the first year of operation.
  • ๐Ÿ‘ท Jobs promised100

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 9, 2025
    Meta announced an $800 million, 715,000-square-foot data center on 280 acres in Middleton Township.
  • May 28, 2026
    A request was filed to rezone 13 more parcels (about 32 acres) owned by Meta for construction use.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Regional Growth Partnership and JobsOhio welcome Meta to Northwest Ohio with new $800 million data center announcement ยท JobsOhio ยท April 9, 2025
  2. New $800 million Meta data center coming to Wood County ยท WTVG 13abc ยท April 9, 2025
  3. Rezoning request filed for 32 acres surrounding the Meta data center site ยท BG Independent News ยท May 2026

See something wrong? Tell us and we'll fix it.