Built & runningBig (AI-size): 221 megawatts

Bitdeer crypto mining site (Massillon)

Also called: Bitdeer Massillon Facility

Bitdeer runs a large bitcoin mining site on Massillon's southwest side that can use up to 221 megawatts. It built a 30- to 40-foot sound wall near homes and promised to stay at 60 decibels or less at the property line. It gets city water and got no property tax break.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Built & running Mining began in November 2025. About half built in June 2026; all 24 buildings due by end of summer 2026.

❓ 1 open question about it: see below.

📣 Report noise, water or power bill changes

Last checked Oct 7, 2026.

🕒 Latest update (April 6, 2026): Massillon City Council passed a 180-day pause on new data centers.

What we know

  • 📍 Where1115 Industrial Ave. SW, Massillon, Stark County
  • 🏢 CompanyBitdeer Technologies
  • 🏛️ Owned byBitdeer Technologies Group
  • 👤 Built forBitdeer (bitcoin mining)
  • ⚡ Power it needs221 megawatts (about as much as 176,800 homes)
  • 🔌 Where the power comes fromGrid power through the company's own substation next to a FirstEnergy substation
  • 💧 WaterCity of Massillon
  • ❄️ CoolingOutside air with wet 'water wall' pads in summer
  • 💵 Cost$100 million
  • 💸 Tax breaksNo property tax break, per the company.
  • 👷 Jobs promised70

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water does it use on hot summer days? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Nov 2025
      First bitcoin mining machines started running.
    • April 6, 2026
      Massillon City Council passed a 180-day pause on new data centers.

    Local votes and rules

    📜 Data center rules

    City council voted 7-1 to allow data centers only in heavy industrial (I-2) zones, at least 400 feet from homes. Developers must show there is enough water, power and sewer capacity, and certify peak noise levels. This replaced the city's pause (moratorium).

    Aug 3, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. What's it like inside Bitdeer's crypto mining operation in Massillon? (Canton Repository) · Canton Repository via Yahoo Finance · June 2, 2026
    2. Supporters see opportunity. Critics see risk at Canton data center forum (Canton Repository) · Canton Repository via AOL · July 15, 2026
    3. U.S. Census Geocoder result for 1115 Industrial Ave SW, Massillon, OH · U.S. Census Bureau · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.