Approved, not built yet

Two data center campuses next to AWS on Industrial Parkway and Warner Road (Jerome Township)

Also called: Thomas industrial development, Starkey industrial development, 8510 Warner Road LLC

A developer filed plans for 11 data center buildings on about 215 acres beside Amazon's campuses in Jerome Township. The township first said no over noise and glare rules, then issued two zoning certificates in December 2025. No company has said who would use them.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 6, 2026

Where things stand: The township first denied zoning certificates in September 2025. In December 2025 it issued two zoning certificates for data centers along Industrial Parkway and Warner Road.

πŸ•’ Latest update (Dec 2025): Jerome Township issued two zoning certificates for data centers tied to the Thomas and Starkey developments on Industrial Parkway and Warner Road.

What we know

  • πŸ“ WhereNext to Amazon sites at 8657 Warner Road and 8619 Industrial Parkway, Jerome, Union County
  • 🏒 CompanyCivil Solutions (engineer for the filings); land owner 8510 Warner Road LLC
  • 🌳 Size215 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 2025
    Plans filed for two campuses with 11 data center buildings next to Amazon's Jerome Township sites.
  • Sept 3, 2025
    Jerome Township denied the zoning certificates and approved a nine-month pause on new data centers that did not apply to these filings.
  • Dec 2025
    Jerome Township issued two zoning certificates for data centers tied to the Thomas and Starkey developments on Industrial Parkway and Warner Road.

Local votes and rules

πŸ—ΊοΈ Zoning change

Township trustees changed data centers from an allowed use to a 'conditional use.' That means each new data center needs special approval.

March 17, 2026

⏸️ Pause on new data centers

Township trustees unanimously passed a nine-month pause (moratorium) on new data centers, after residents complained about noise from existing data centers. It ended in June 2026.

Sept 3, 2025
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Developer files plans for two large-scale data center campuses adjacent to AWS in Jerome Township, OH Β· New Project Media Β· 2025
  2. Data centers still knocking on Jerome's door Β· Marysville Journal-Tribune Β· Feb 2, 2026

See something wrong? Tell us and we'll fix it.