Built & running
MARA bitcoin mining site (Hopedale)
Also called: MARA Hopedale Data Center
MARA owns a bitcoin mining site in Hopedale that was already running when it bought it in 2024. A local candidate described a constant humming sound from the site.
Where things stand: Running when MARA bought it in November 2024.
๐ Latest update (Nov 5, 2024): MARA bought the running Hopedale and Hannibal mining sites.
What we know
- ๐ WhereHopedale, Harrison County
- ๐ข CompanyMARA Holdings
- ๐๏ธ Owned byMARA Holdings
- ๐ค Built forMARA (bitcoin mining)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts does the Hopedale site use? ๐ I'll find out
What happened so far
- Nov 5, 2024MARA bought the running Hopedale and Hannibal mining sites.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- MARA Adds 372 Megawatts of Capacity in Ohio ยท MARA Holdings ยท Nov 11, 2024
- Proposed 'Stargate Ohio' project draws Belmont County into data center conversation ยท The Times Leader ยท June 2026
See something wrong? Tell us and we'll fix it.