USA โ€บ Ohio โ€บ Monroe County โ€บ Ohio Township
Proposed

Bitdeer AI computing campus at Hannibal Industrial Park (former Ormet site)

Also called: Bitdeer Clarington, Erie Creek LLC

Bitdeer leased land at the old Ormet aluminum plant site near Hannibal and says it could get up to 570 megawatts of power there for AI computing. A steel company in the same industrial park sued, saying the project would interfere with its power, roads and rail. Bitdeer says the lawsuit could delay the project.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Bitdeer has a 30-year lease, but a neighboring company sued in 2026 to stop construction. The case is pending.

๐Ÿ•’ Latest update (Feb 2, 2026): A steel company leasing part of the park sued Bitdeer and the port authority in Monroe County court to protect shared roads, power and rail.

What we know

  • ๐Ÿ“ WhereHannibal Industrial Park, former Ormet aluminum plant, along the Ohio River near Hannibal, Ohio, Monroe County
  • ๐Ÿข CompanyErie Creek LLC
  • ๐Ÿ›๏ธ Owned byBitdeer Technologies Group
  • โšก Power it needs570 megawatts (about as much as 456,000 homes)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2021
    Monroe County Port Authority bought the former Ormet property.
  • 2024
    Bitdeer announced a 30-year lease with the port authority and access to up to 570 megawatts of power.
  • Feb 2, 2026
    A steel company leasing part of the park sued Bitdeer and the port authority in Monroe County court to protect shared roads, power and rail.
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Bitdeer Data Center Plans Face Lawsuit at Former Ormet Site ยท River News Network ยท June 3, 2026
  2. Bitdeer Technologies Group Form 6-K (legal proceedings) ยท U.S. Securities and Exchange Commission ยท Feb 5, 2026