Send us a tip
ProposedBig (AI-size): 425 acres

Possible data center near Cambridge airport area (Guernsey County)

Also called: Undisclosed Data Center (Miller Property)

A landowner with 425 acres and an energy adviser told Guernsey County commissioners they are studying a data center with its own gas power. Commissioners said they are against it, but the county has no zoning to stop it. Residents formed a group to oppose it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Where things stand: Proposed Only early talks; no formal plan. County commissioners say they oppose it but have no zoning power.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (June 16, 2026): County commissioners announced they oppose the data center. They said the county has no zoning, so they cannot approve or deny it.

What we know

  • 📍 WhereAbout 425 acres; meeting minutes mention the airport area south of Cambridge, Guernsey County
  • 🏢 CompanySmart Energy Partners (adviser to a local landowner)
  • 🌳 Size425 acres
  • 🔌 Where the power comes fromOn-site natural gas power (behind the meter), per meeting minutes

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the site? 🙋 I'll find out ·
  • Will a developer file a formal plan or ask for a tax break? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 9, 2026
      A landowner and Smart Energy Partners presented the idea to county commissioners.
    • June 9, 2026
      Developers described a possible data center to Guernsey County commissioners at an open meeting. They did not say where it would go.
    • June 16, 2026
      County commissioners announced they oppose the data center. They said the county has no zoning, so they cannot approve or deny it.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Guernsey County sees proposal for a data center · WOUB Public Media · June 23, 2026
    2. Opposition to Proposed Data Center (press release) · Guernsey County Commissioners · June 16, 2026

    See something wrong? Tell us and we'll fix it.