Being builtBig (AI-size): 150 megawatts

MARA Findlay data center (crypto mining)

MARA, a bitcoin mining company, is building a 150-megawatt computer site in Findlay. About 30 megawatts were running in late 2024.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Findlay City.

Where things stand: Being built Announced November 2024 with 30 megawatts running and plans for 150 megawatts.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Nov 11, 2024): MARA said it was building a 150-megawatt site in Findlay, with 30 megawatts already running.

What we know

  • 📍 WhereFindlay, Hancock County
  • 🏢 CompanyMARA Holdings
  • 👤 Built forMARA (bitcoin mining)
  • ⚡ Power it needs150 megawatts (about as much as 120,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly is the MARA site, and is it inside Findlay city limits or in a township? 🙋 I'll find out ·
  • How much of the 150 megawatts is running now? 🙋 I'll find out ·
  • Is it noisy for neighbors, and is there a noise limit? 🙋 I'll find out ·
  • Where exactly is MARA's Findlay bitcoin site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Nov 11, 2024
      MARA said it was building a 150-megawatt site in Findlay, with 30 megawatts already running.

    Local votes and rules

    📜 Data center rules

    Findlay is working on data center rules during its pause. The draft includes setbacks, noise limits, outside technical reports paid for by the developer, and a case-by-case cap on how much power a data center can use.

    Sept 2026

    ⏸️ Pause on new data centers

    City council passed a one-year pause (moratorium) on new data centers. It is set to end in April 2027.

    April 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. MARA Adds 372 Megawatts of Capacity in Ohio · MARA Holdings · Nov 11, 2024