ProposedBig (AI-size): 500 megawatts

M2 Development data center study at Conneaut East Industrial Park

M2 Development Solutions is studying a data center of about 500 megawatts at the Conneaut East Industrial Park, powered by natural gas. No formal plan has been filed. In November, Conneaut voters will decide a charter change that would cap data centers at 25 megawatts.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Conneaut City.

Where things stand: Proposed Only a feasibility study so far; no proposal filed. On Nov. 3, 2026 voters approved a charter ban on data centers over 25 megawatts (unofficial results).

  • Nov 3, 2026: Conneaut, Ashtabula County: referendum decided Source

❓ 4 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (Nov 3, 2026): Conneaut voters approved a city charter change banning data centers over 25 megawatts, by about 3 to 1 (unofficial results).

What we know

  • 📍 WhereConneaut East Industrial Park, Conneaut, Ashtabula County
  • 🏢 CompanyM2 Development Solutions
  • ⚡ Power it needs500 megawatts (about as much as 400,000 homes)
  • 🔌 Where the power comes fromNatural gas power, per the developer
  • ❄️ CoolingAir cooling, per the developer

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will M2 file a formal proposal with the city? 🙋 I'll find out ·
  • Would the gas power plant be on site, and what air permits would it need? 🙋 I'll find out ·
  • Does the new Conneaut charter ban on data centers over 25 megawatts stop the M2 Development plan? 🙋 I'll find out ·
  • Has M2 Development said what it will do after the Nov. 3, 2026 vote? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2026
      Conneaut City Council voted down a one-year data center pause.
    • Sept 2026
      A citizen charter amendment to cap data centers at 25 megawatts qualified for the November ballot.
    • Nov 3, 2026
      Conneaut voters approved a city charter change banning data centers over 25 megawatts, by about 3 to 1 (unofficial results).

    Local votes and rules

    🗳️ Public vote

    Voters approved a city charter change that bans data centers that use more than 25 megawatts of power, by about 3 to 1. Results are unofficial until the county elections board certifies them (expected in late November 2026).

    Nov 3, 2026

    🗳️ Public vote

    Voters will decide a city charter change that would ban data centers that use more than 25 megawatts of power.

    Nov 3, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center developer shares perspective, speaks on feasibility study (Star Beacon) · Star Beacon via Yahoo News · Sept 26, 2026
    2. How Northeast Ohio voted on data center issues in the Nov. 3 general election · WJW Fox 8 Cleveland · Nov 8, 2026
    3. Data centers go 0-for-21 in ballot initiatives around Ohio · Ohio Capital Journal · Nov 9, 2026

    See something wrong? Tell us and we'll fix it.