A Westlake company proposed a $1.6 billion, 150-megawatt data center on 35 acres in Cleveland's Slavic Village. Neighbors and a council member raised concerns, and the city rejected the permit in May 2026.
What happens next?
Where things stand: Stopped or cancelled The city rejected the permit on May 14, 2026.
❓ 1 open question about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 7, 2026.
🕒 Latest update (May 14, 2026): The city rejected the permit application.
What we know
- 📍 Where3560 E. 55th St., Slavic Village (old Morabito Enterprises trucking property), Cleveland, Cuyahoga County
- 🏢 CompanyLakeland Equity Group
- 🌳 Size35 acres
- ⚡ Power it needs150 megawatts (about as much as 120,000 homes)
- 💵 Cost$1.6 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has Lakeland appealed or filed a new plan? 🙋 I'll find out ·
What happened so far
- May 2026Lakeland Equity Group proposed Cleveland's first hyperscale data center.
- May 4, 2026Councilman Charles Slife introduced a data center pause ordinance.
- May 14, 2026The city rejected the permit application.
Local votes and rules
⏸️ Pause on new data centers
A council member planned to introduce a 90-day extension of Cleveland's pause on new stand-alone data centers, so the city has more time to write rules. The first pause passed in July 2026.
⏸️ Pause on new data centers
City council extended its pause on new stand-alone data centers, and on growing existing ones, to Jan. 29, 2027. The pause ends sooner if the city adopts new data center rules. Existing data centers can keep running.
⏸️ Pause on new data centers
City council passed a three-month pause (moratorium) on new data centers. It is set to end in October 2026.
✋ Turned down
The city rejected a permit for a $1.6 billion, 150-megawatt data center campus on 35 acres between Slavic Village and the Industrial Valley. A city spokesperson said it did not pass zoning review.
Drag the slider to compare the land before and now.
Where this comes from
- City rejects permit application for proposed data center in Cleveland's Slavic Village neighborhood · Cleveland 19 · May 14, 2026
- $1.6bn Cleveland data center plan rejected · Baxtel · May 2026
- U.S. Census Geocoder result for 3560 E 55th St, Cleveland, OH · U.S. Census Bureau · Oct 7, 2026
See something wrong? Tell us and we'll fix it.